BUS 407 Project Management - Emirates College of Technology
Case Study: Risk Management and Evaluation
Nuclear energy is one of the possible alternative energy to meet the increasing energy demand in the world. Unlike coal and gas, nuclear power can be considered as clean from pollution. In this context, the UAE has increased its focus on this energy in order to comply with its vision of being a clean industrial country that sustain environment and people. As the risk manager of a project sponsored by Barakah, you are assigned the role of managing and evaluating risks that might affect the project during the execution phase. The project is scheduled to start from July 2021, it consists of power plant extension that include expanding the power plant building and installing new electrical machines to boost the produced electric power. During a brain storming session, you discovered that the current pandemic, due the COVID-19, could be a triggering event that might lead to the occurrence of several risky events. The following represents data about the project prior to the risk study:
Activity |
Description |
Immediate Predecessor |
Activity Time : T |
(in days) |
|
|
|
A |
Plant specifications study |
- |
5 |
B |
environmental impact study |
A |
6 |
C |
Engineering study |
A |
8 |
D |
Demolition, remodeling, and dust control |
B |
12 |
E |
Enter additional electrical machines and equipment |
B |
20 |
F |
Job-site security |
B,C |
16 |
G |
On site execution of the building extension |
D,E |
25 |
H |
On site execution of the machinery implementation |
F |
35 |
I |
Testing the new building with machines onboard |
F |
20 |
J |
security control and safety monitoring |
G,H,I |
14 |
Table: Power Plant Extension Project - Data
Part I: Risk Management
As the head of the project risk management team, you will perform some of the risk management steps by replying to the following questions:
Questions:
Propose four possible risk events that could be triggered by the COVID-19 pandemic and explain how they might affect the project.
For each proposed risk event, propose a risk response plan to face or overcome the risk (Note that risk response plans should be different for each risk event).
Attachment:- Individual Project.rar
How much is the carrying amount of the patent on december
: How much is the carrying amount of the patent on December 31, 2020? On January 1, 2016, J-Hope Company incurred a P2,500,800 cost to develop
|
Journalize the entry to record the factory labor costs
: Factory overhead is applied to jobs on the basis of a predetermined overhead rate of $23 per direct labor hour. Journalize entry to record factory labor costs
|
Learn about an opportunity
: Research it until you find and learn about an opportunity or problem related to it. Focusing on this specific opportunity or problem,
|
What is the loss reported in the income statement
: Jungkook Company has a single investment property, What is the loss reported in the income statement for 2020 under the fair value model?
|
Propose a risk response plan to face or overcome the risk
: Propose a risk response plan to face or overcome the risk (Note that risk response plans should be different for each risk event)
|
Defining the future strategic direction of health care
: Describe a minimum of five challenges from the list below that are defining the future strategic direction of health care.
|
What is the franchise cost on december
: Initial franchise fee P4,320,000. The entity used 2 decimal places for the PV factor. What is the franchise cost on December 31, 2021?
|
Determine the direct labor cost
: Total manufacturing costs for the period 7,880,000 and Materials inventory, end of period 290,000. Determine the direct labor cost
|
Cost of litigation can be costly and timely
: Arthur's business is located in Chippewa Falls, Wisconsin. Suzanne knows that the cost of litigation can be costly and timely.
|