Project selection - annual earnings approximate cash flows

Assignment Help Project Management
Reference no: EM1343376

Project selection : explained

The following investment opportunities are available to an investment center manager.

Project Initial Investment Annual Earnings
A $800,000 $90,000
B $100,000 $20,000
C $300,000 $25,000
D $400,000 $60,000

a. If the manager currently makes a return of 16%, which project(s) would the manager want to pursue?

b. If the cost of capital is 10% and the annual earnings approximate cash flows excluding finance charges, which project(s) should be chosen?

c. Suppose only one project can be chosen and the annual earnings approximate cash flows excluding finance charges, which project should be chosen?

Reference no: EM1343376

Questions Cloud

Important information about project management plan : Analyze the role of project management in creating and maintaining facility assets and explain internal factors that affect project management decisions within facilities management of a resort hotel.
Culture on the role and authority of the project manager : Important information about organization's structure and culture - explain what are the effects of an organization's structure and culture on the role and authority of the project manager?
Important for successfully completing a project : The project management structure or the culture of the organization - Important for successfully completing a project
How might goals be measured for feasibility : Does the system offer adequate controls to protect against fraud and embezzlement and to guarantee the accuracy and security of data and information?
Project selection - annual earnings approximate cash flows : Suppose only one project can be chosen and the annual earnings approximate cash flows excluding finance charges, which project should be chosen?
Question about financial systems : Explain what are the economic functions financial intermediaries perform and what is the role of broker in the financial market
Project operations management question : How much cash should the bank keep at an ATM if its annual cost of money is 10% and how often should the bank replenish an ATM
Project management - managing risks : Project Management - Find some items that might go wrong during this type of project
Macro and micro project risk management : Macro and Micro project risk management - describe the difference between Macro and Micro risk management.

Reviews

Write a Review

Project Management Questions & Answers

  Prerequisites for using bayesian statistics

What are some prerequisites for using Bayesian statistics?

  Show the simulation methods

Simulation Methods - Describe the possible benefits to using one of the simulation methods when assessing for possible project risks.

  Computing optimal production size for fertilizer

Compute the optimal production size for the fertilizer.

  Work breakdown structure differ from the project network

How does the Work Breakdown Structure differ from the Project Network (Diagram)?

  Explaining modern history of project management

History of Project Management Describe the modern history of project management. Identify major contributors to the discipline, as well as significant events in its history.

  Create weeklong work schedule to meet needs of employee

Create a weeklong work schedule to meet the needs of the employees, the customers, and therestaurant.

  Explain what challenges might the foreign managers face

Explain what challenges might the foreign managers face while communicating with the home base and justify your answer with examples and reasoning.

  Critical issues faced by managers

Identify the most critical issues faced by managers with regard to the topic.

  Computing value of the depreciation tax shield

The company has a marginal tax rate of 34 percent. What is the value of the depreciation tax shield?

  Implementation of good disaster prevention procedures

A business disaster takes place when, despite the implementation of good disaster prevention procedures, normal business operations stop.

  Classify costs associated with operation of a factory

Classify costs associated with operation of a factory - depreciation on cafeteria equipment and insurance on a building used in producing helicopters

  Computing reward to risk ratio for project

The expected return and standard deviation of project B is 25% and 20%, respectively. The risk-free rate is 8%. What is the reward to risk ratio for project A?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd