Reference no: EM13737130
Assignment: Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
Health insurance portability and accountability act
: In this assignment, you will list the forms that you will be reviewing with a new patient to accommodate the Health Insurance Portability and Accountability Act (HIPAA) policies and procedures.
|
Find any destination for sustainable tourism in the us
: Sustaining Tourism's Benefit, please search the Internet to find any destination for sustainable tourism in the US and briefly discuss why the destination of your choice could be examples/cases of sustainable tourism
|
Perform an internal competitive environment scan for apple
: Complete the external environment scan for Apple Inc. Perform an internal competitive environment scan for Apple
|
Change the supply of and demand for labor
: Factors affecting variable costs, including productivity and others that change the supply of and demand for labor - strategic planning group
|
Project schedule changes
: You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
|
Key strategy that managers may use
: From the first e-Activity, suggest one (1) key strategy that managers may use in order to combat workplace stress productively in today's work environment. Provide support for your strategy
|
Choose two of the cqi methodologies
: Choose two of the CQI methodologies (PDSA, Lean or SixSigma). How do these methodologies utilize data. Discuss the significance of the collection and analysis of data in CQI processes.
|
Identify three or more competitive strategies
: Identify the market structure in which this organization competes. Clearly indicate why the market structure was decided upon, and how this market structure differentiates from the other alternatives.
|
Distribution strategy relative to your target market
: Consider the marketing materials that you intend to use. According to the textbook, marketing materials are collateral used to promote your business or products. Determine the distribution strategy relative to your target market, location, and sele..
|