A project is expected to create operating cash flows of $22,500 a year for three years. The initial cost of the fixed assets is $50,000. These assets will be worthless at the end of the project. An additional $3,000 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 10 percent?

Reference no: EM1339939

Questions Cloud

Motivations and consequences of expansion : What are some of the motivations and consequences of expansion that led us into involvement with other nations?
Explain four factors of copyright infringement : Explain Four Factors Of Copyright Infringement and the purpose of the copies (educational purposes are less likely to be infringement than commercial purposes) and the market effect
Computing earnings before interest and taxes : The sale price is estimated at $14 a unit, give or take 5 percent. What is the earnings before interest and taxes under the BEST case scenario?
Effect of the price increase on the firm''s fcf : Chip's Home Brew Whiskey management forecasts that if the firm sells each bottle of Snake-Bite for $20, then the demand for the product will be 15,000 bottles per year, determine  the effect of the price increase on the firm's FCF for the year
Project-s net present value if rate of return is given : What is the project's net present value if the required rate of return is 10 percent?
Controversial document : Why was the Constitution a controversial document, even as it was being written?
Explain why are they in such universal agreement : Economists are in almost universal agreement that Free Trade is good for all countries. Explain why are they in such universal agreement.
Explain how has the sarbanes-oxley act : Explain How has the Sarbanes-Oxley Act (SOX) changed the system of corporate governance
Calculate wacc after tax : Capital Co. has a capital structure, based on current market values, that consists of 34 percent debt, 12 percent preferred stock, and 54 percent common stock.  Calculate WACC after tax in percent.

Reviews

Write a Review

Project Management Questions & Answers

  Project scope and schedule for wal-mart

How would a consultant develop the project scope and schedule for Wal-mart?

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Risks introduced by change in plans

What are the risks (adverse effect) that are introduced by this change in plans?

  Determining early and late start and finish times

Determine the early and late start and finish times and the slack times for the activities. Identify the critical path.

  Project manager-s effectiveness and reliability

A project manager's effectiveness is limited by the thoroughness, reliability, validity, and honesty of the performance measurement system employed.

  Preparing presentation appropriate for the audience

Was Terry's presentation appropriate for the audience?

  Evaluating potential projects before implementing it

Why do you think it is important to evaluate potential projects before proceeding with implementation?

  Computing number of units to purchase

Projected sales for August, September, and October are 25,000 units, 20,000 units, and 30,000 units, respectively. How many units must be purchased in September?

  Importance of project sponsorship and leadership

Describe the importance of project sponsorship and leadership when it comes to escalating decisions during a project.

  Computing appraisal cost for quality last year

The following table lists all costs of quality incurred by Sam's Surf Shop last year. What was Sam's appraisal cost for quality last year?

  Sensitive is operating cash flow to changes in quantity

How sensitive is Operating Cash Flow (OCF)to changes in quantity sold? State your answer in terms of a dollar amount change (increase or decrease) in OCF for every additional unit sold.

  Project-program and portfolio management

Describe the difference between project, program, and portfolio management.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd