Project problem cost of home improvement for resalemrs

Assignment Help Project Management
Reference no: EM13363378

Project Problem: Cost of Home Improvement for Resale

Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans for the house show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing himself. Mrs. Tolstoy feels she can take care of the interior decorating.

The following average cost information is available from a local bank that makes loans to local contractors and disperses progress payments to contractors when specific tasks are verified as complete.

24% Excavation and framing complete
8% Roof and fireplace complete
3% Wiring roughed in
6% Plumbing roughed in
5% Siding on
17% Windows, insulation, walks, plaster, and garage complete
9% Furnace installed
4% Plumbing fixtures installed
10% Exterior paint, light fixtures installed, finish hardware installed
6% Carpet and trim installed
4% Interior decorating
4% Floors laid and finished

a.What is the estimated cost for the Tolstoy's house if they use contractors to complete all of the house?
b.Estimate what the cost of the house would be if the Tolstoys use their talents to do some of the work themselves.

Reference no: EM13363378

Questions Cloud

Contemporary planning techniques reccomendationtoday many : contemporary planning techniques reccomendationtoday many organizations and managers face new challenges every day. one
Project acceptanceaerospace dynamics will invest 110000 in : project acceptanceaerospace dynamics will invest 110000 in a project that will produce the following cash flows. the
What are the benefits of project managementprovide an : what are the benefits of project management?provide an example of how you have relied on project management.based on
Project selectionmountain ski corp was set up to take large : project selectionmountain ski corp. was set up to take large risks and is willing to take the greatest risk possible.
Project problem cost of home improvement for resalemrs : project problem cost of home improvement for resalemrs. tolstoy and her husband serge are planning their dream house.
Project managemet work break down structureyour next step : project managemet work break down structureyour next step in the project management process is to create a work
Project management solutiona project has a specific time : project management solutiona project has a specific time frame or finite life span. it has a start time and a date by
Tax effect of loss on sale of asset at the end of a : tax effect of loss on sale of asset at the end of a projectsuppose an asset is sold for less than its book value at the
Important information about project proposalprepare a : important information about project proposalprepare a project proposal how to lead and meet the needs of the customer

Reviews

Write a Review

Project Management Questions & Answers

  What is the difference between negligence and strict

What is the difference between negligence and strict liability? What are some of the latest amendments to the Truth-in-Lending Act?

  Network diagram and identify all the pathgiven the

network diagram and identify all the pathgiven the information in the following tableactivity duration predecessora 4

  Terminal cash flows at end of the project

Explain what is the one time cash flows - terminal cash flow associiated with ending the project?

  Efficiency and expertise in performance improvement

Because of your great efficiency and expertise in performance improvement, you have been reassigned to a project that is behind schedule due to the loss of several key staff members.

  Project with real cash flows versus nominal cash flows

Can you think of a project for which it might be easier to project real cash flows than to project nominal cash flows?

  Manager-managed llc

Lynda will be allowed to participate, but is not entitled to any compensation

  Show the project management solution

Project Management solution - Explain what are some implications of completing a project before the scheduled completion date

  Micro-managementexplain what are the advantages and

micro-managementexplain what are the advantages and disadvantages of micromanagement? what are the advantages and

  Project managementassume you work in a small firm that has

project managementassume you work in a small firm that has multiple projects happening simultaneously and that the

  According to carroll the responsibility that management

According to Carroll, the responsibility that management of a business organization has to produce goods and services of value to society

  Managerial decision making

How could the fixed pie concept come into play in this situation and Managerial Decision Making

  What was salems expected net present value for this project

Present value information is given below so what was Salem's expected net present value for this project

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd