A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activity is given. You have been asked by your supervisor to prepare a research paper that addresses the follow criteria:

- What is the probability that the project will be completed in 32 weeks or less?

- If the project is to be shortened by four days, list the process you would take to determine which activities, in order of reduction, would be shortened and the resulting cost.

- Describe project cost and the requirements for it's determination and application in a production facility.

- Analyze implications of changes in the parameters of project timing and cost determination.

- Evaluate application of project cost and timing concepts on a firm's business operations.

Reference no: EM13114569

Questions Cloud

Illustrate what recommendations would you make to senior : Illustrate what recommendations would you make to senior management for the upcoming year? Note that stating you have no advice or that management should keep doing what they have been doing.
Compute confidence level for difference in means : Compute a 95% confidence level for the difference in the means of the two treatment methods and select the best answer below. Assume that the independent random samples were taken from normal distribution.
Provide a possible explanation : Provide a possible explanation as to why this test identifies the presence of cytochrome c oxidase and not the other electron carries.
Compare and contrast how quality new products : Compare and contrast how quality new products/services are likely to be developed at a McDonald's versus a bank in your neighborhood.
Project probability with variance : A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activ..
What controls should an organization : What controls should an organization like Tyco implement to ensure that such transactions do not take place in the future?
Use t test for dependent means and independent means : For each of the following studies, say whether you would use a t test for dependent means or a t test for independent means.
How many kilograms of methane is present : How many kilograms of methane (CH4) are in perfectly insulated piston with the following properties: Volume = 2 cubic meters.
Describe the unwinding process or the synthesis : A piece of DNA has unwound and the ends of the two strands have begun separating for replication. Describe, in full detail, the discontinuous synthesis of the lagging strand.

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Relationship between speed, flow and geometry

Write a project proposal on relationship between speed, flow and geometry on single carriageway roads.

  Logistic regression model

Compute the log-odds ratio for each group in Logistic regression model.

  Logistic regression

Foundations of Logistic Regression

  Probability and statistics

The tubes produced by a machine are defective. If six tubes are inspected at random , determine the probability that.

  Solve the linear model

o This is a linear model. If your model needs a different engine, then you need to rethink your approach to the model. Remember, there are no IF, Max, or MIN statements in linear models.

  Plan the analysis

Plan the analysis

  Quantitative analysis

State the hypotheses that you are going to test.

  Modelise as a markov chain

modelise as a markov chain

  Correlation and regression

What are the degrees of freedom for regression

  Construct a frequency distribution for payment method

Construct a frequency distribution for Payment method

  Perform simple linear regression

Perform simple linear regression

  Quality control analysis

Determining the root causes

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd