Project probability with variance

Assignment Help Advanced Statistics
Reference no: EM13114569

A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activity is given. You have been asked by your supervisor to prepare a research paper that addresses the follow criteria:

- What is the probability that the project will be completed in 32 weeks or less?

- If the project is to be shortened by four days, list the process you would take to determine which activities, in order of reduction, would be shortened and the resulting cost.

- Describe project cost and the requirements for it's determination and application in a production facility.

- Analyze implications of changes in the parameters of project timing and cost determination.

- Evaluate application of project cost and timing concepts on a firm's business operations.

Reference no: EM13114569

Questions Cloud

Illustrate what recommendations would you make to senior : Illustrate what recommendations would you make to senior management for the upcoming year? Note that stating you have no advice or that management should keep doing what they have been doing.
Compute confidence level for difference in means : Compute a 95% confidence level for the difference in the means of the two treatment methods and select the best answer below. Assume that the independent random samples were taken from normal distribution.
Provide a possible explanation : Provide a possible explanation as to why this test identifies the presence of cytochrome c oxidase and not the other electron carries.
Compare and contrast how quality new products : Compare and contrast how quality new products/services are likely to be developed at a McDonald's versus a bank in your neighborhood.
Project probability with variance : A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activ..
What controls should an organization : What controls should an organization like Tyco implement to ensure that such transactions do not take place in the future?
Use t test for dependent means and independent means : For each of the following studies, say whether you would use a t test for dependent means or a t test for independent means.
How many kilograms of methane is present : How many kilograms of methane (CH4) are in perfectly insulated piston with the following properties: Volume = 2 cubic meters.
Describe the unwinding process or the synthesis : A piece of DNA has unwound and the ends of the two strands have begun separating for replication. Describe, in full detail, the discontinuous synthesis of the lagging strand.

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Decision making-solution set

Considering Bazerman's writing about Framing and the reversal of preferences and Motivational and Affective Influences on decision making, write a paper, responding to the assigned write-up.

  Link between relative frequency and the cumulative frequency

What is the purpose of developing a frequency distribution? What is the relationship between the relative frequency and the cumulative frequency?

  Calculate the equation of the regression line

Which is the explanatory variable and draw a scatterplot on your calculator and comment on the form, direction, and strength of the data.

  Statisticians working with clinical researchers

The problems for this assignment are typical of those encountered by statisticians working with clinical researchers. So if you'll humor me, I have written this assignment as though it is a day in the life of a project statistician.  Here is your age..

  Relative frequency approach

A calculus instructor uses computer aided instruction and allows students to take the midterm exam as many times as needed until a passing grade is obtained.

  Techniques in business-economics

A sample of the monthly amounts spent for food by families of four receiving food stamps approximates a symmetrical distribution. The sample mean is $150 and the standard deviation is $20.

  Information about research and evaluation

Explain primary data and describe at least three types and how they are gathered. Explain the financial aspect of secondary data. How has the internet changed research processes

  Consensual relationship agreements

Create a counter argument against the use of CRAs in your current (or future) workplace. Discuss the ethical principles involved in the use of CRAs. Create at least one (1) other option besides CRAs that would address workplace romances.

  Notions of mathematical differences

Explain the notions of mathematical differences, managerially important differences, and statistical significance. Can results be statistically significant and yet lack managerial importance.

  Organizational behavior and decision making process

Decision making is a form of deductive reasoning; it is a strategic study that identifies alternatives that would be feasible for many organizations to proceed with general business practices.

  Do a one-way anova to test the hypothesis

Do a one-way ANOVA to test the hypothesis that the population means are equal and what are the hypotheses to be tested here? What is the value of F ?

  Product learning process

A new product learning cycle indicates companies learning from product failure or mistake they made. In business, especially technology, it is important to learn from failure and continue improving.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd