Project plan to reflect revisions based upon risks

Assignment Help Marketing Management
Reference no: EM13548703

You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.

You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.

In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.

Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.

You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.

You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.

Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.

Submit both your updated project plan and PowerPoint presentation.

Submit your plan to M4: Assignment 2 Dropbox by Wednesday, August 13, 2014. Assignment 2 Grading Criteria

Maximum Points Correctly updated the project plan to reflect revisions based upon risks and details presented. 50 Created a senior level presentation detailing the recommendations and seeking approval. 45 Used correct grammar, spelling, and word choice and cited all sources using correct APA style. 5 Total: 100

Reference no: EM13548703

Questions Cloud

What is the final angular speed of the merry-go-round : A disk-shaped merry-go-round of radius 3.02 m and mass 159 kg rotates freely with an angular speed of 0.635 rev/s. A 54.1-kg person running tangential to the rim of the merry-go-round at 3.07 m/s jumps onto its rim and holds on. Before jumping on the..
Closing entries with net income : Journalize the entries required to complete the closing of the accounts and determine the amount of Retained Earnings at the end of the period.
Find the maximum angular speed possible for this motor : A motor has a single loop inside a magnetic field of magnitude 0.581 T. If the area of the loop is 305.0 cm2, find the maximum angular speed possible for this motor
What is the work done on the block by the spring : A block of mass is pushed up against a spring with spring constant until the spring has been compressed a distance from equilibrium. What is the work done on the block by the spring?
Project plan to reflect revisions based upon risks : Project plan to reflect revisions based upon risks
Estimate the direction and magnitude of the induced current : An elastic circular conducting loop expands at a constant rate over time such that its radius is given by r(t) = r0 + vt, where r0 = 0.170 m and v = 0.0290 m/s. estimate the direction and the magnitude of the induced current
Fundamental frequency-cause standing-wave patterns on string : A string that is 20.0 cm long and has a mass per unit length of 8.00 10-3 kg/m is stretched to a tension of 18.0 N. (a) Find the fundamental frequency. f1 = Hz (b) Find the next three frequencies that could cause standing-wave patterns on the string...
What is ewalds stock price 5 years from now : If dividends are expected to grow at a constant rate g in the future, what is Ewald's stock price 5 years from now?
Determine the magnification produced by the mirror : A convex mirror has a focal length of -30 cm. Find the magnification produced by the mirror when the object distance is 8 cm

Reviews

Write a Review

Marketing Management Questions & Answers

  Integrated marketing communication

Developing an IMC plan of Amazon that aims to create awareness and knowledge amongst Singaporean  consumers of the ethics involved in buying clothing made from Bangladeshi factories  .

  Multiple choice questions on e-commerce

The assignment in Computer Science or Information Technology is about multiple choice questions, particularly in e-commerce. Questions such as types of e-commerce websites, commercial websites, disintermediation, Platform for Piracy, the data that ca..

  Balanced scorecard for red lobster

The assignment in marketing is about Red Lobster, which is one US and Canada's most loved seafood restaurant. It has hundreds of outlets in US and Canada and it now wants to expand further. The approach adopted by Red Lobster has been discussed in fu..

  Marketing plan - marketing audit, swot and smart report

The assignment in marketing is about preparing a marketing plan. As part of marketing plan, the SWOT analysis, assessing the competitive position, identifying critical competitive issues, marketing objectives, strategy and actions have been suggested..

  Marketing plan

Marketing deals with preparing a marketing plan for either an existing product or a new product. Various aspects about launching a new product into the market are discussed ranging from the industry the product belongs to, goals and vision of the com..

  Yamato corporation analysis - harvard case study

Please refer to the PDF for the Case Study and questions.The case study from Harvard Business School is about Yamato Corporation, a parcel delivery company which provides door to door delivery in Japan.

  Marketing plan - create a new product

The assignment in marketing is about competitive analysis for a new product namely "heated insoles". These heated insoles can be put in shoes and they can protect the wearer's feet by keeping them warm during cold winters.

  Report on digital marketing strategy for a website

Promotion strategies of  the one's own developed website

  Integrated marketing campaign of mccafe

Integrated marketing campaign for McDonald's McCafe. McCafe has been launched in Canada. This is a case study which involves the use of digital marketing and social media marketing apart from regular marketing such as TV and radio. All these more are..

  New product development at adidas

In this paper, the researcher also determines the different kind of practices used by Adidas to manufacture shoes for its customers.

  Managing services in competitive environment

Services can be defined as separately identifiable, intangible activities which provide want-satisfaction when marketed to household consumers and/or industrial users.

  Prepare a marketing plan

A marketing plan is an essential tool for any marketer, providing direction for a brand, product or organization. A marketing plan describes the marketing environment, marketing objectives and marketing strategies.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd