Project participants revealed the following

Assignment Help Project Management
Reference no: EM131522950

Case Study

PROJECT MANAGEMENT SITUATION ESTABLISHING A PROJECT CONTROL SYSTEM

An organization has been managing projects for several years through a group of project managers, specifically hired for their successes with this type of work. They have consistently performed well in other organizations, demonstrating an exceptional understanding of the technology and the project management discipline. They are excellent communicators and keep all parties informed of the progress of projects.

Recently, the company finance director stated that many of the projects were losing money. This was determined when the new accounting system was implemented and costs for projects were collected, collated, and analyzed. Nearly one-third of the projects were not performing well in the cost area. Only 18 percent of the projects were producing revenues that met the company's fee structure.

A review of project documents and plans as well as discussions with some project participants revealed the following:

  • There was no consistency in the project plans. Some were missing vital information and others were inconsistent with the company's policies for project operations.
  • Each project manager followed a different life-cycle model and methodology for similar projects. There was no single methodology being used for projects.
  • Project managers relied on their experience, methodologies, and styles from their prior organizations.
  • Project managers considered all projects to be successful if they met the cost, schedule, and technical performance objectives. Because cost data were not provided by the accounting department, it was assumed that projects were making money.
  • No project audit had been conducted in at least 3 years and there were no procedures for conducting an audit. No trained people were available to conduct audits. The project managers were hired because they were "experts" in managing projects.

Senior management was in a quandaryâexperienced project managers were not providing the desired cost performance results and there may be other areas that were in need of fixing. Further, the company relied heavily on projects to generate most of its revenue. There was a need for some immediate action to move the company into a better cost performance position.

Case Questions

1. From the information given in the project management situation, what is the most likely problem and how would one fix it?

2. Why do highly qualified project managers use different methodologies in the same company? Is this a problem?

3. What are some of the reasons for lack of meeting cost performance (profit) goals? What can be done to improve the situation?

4. Does the company's project control system work? What, if any, changes should be made?

5. What type of audit would you perform on the projects to determine critical success factors? What would be your initial focus?

PROJECT MANAGEMENT: Strategic Design and Implementation

Reference no: EM131522950

Questions Cloud

Determine the primary and secondary target markets : Determine the primary and secondary target markets for your company. Develop both a SWOT analysis and needs analysis for your product
College level grammar and sentence structure : Write a four-page paper in APA format with college level grammar and sentence structure that describes a project that you might undertake
Explain the key element of richard bransons leadership style : Assess the key elements of Richard Branson's leadership style and the impact that those elements have had on his business success.
Write a program that prints the square of the product : Write code statements to create a DecimalFormat object that will round a formatted value to four decimal places. Then write a statement that uses that object.
Project participants revealed the following : A review of project documents and plans as well as discussions with some project participants revealed the following:
Write a program that prompts for and reads the user city : Write a program that prompts for and reads the user's city and country (separately). Then print a string composed of the first two letters of the user's.
Determining the qualitative risk analysis : What needs to be completed after the qualitative risk analysis? In order to perform a qualitative assessment, what needs to be completed?
Developing a system in a team of members : Discuss advantages and disadvantages of developing a system in a team of members with varying backgrounds/function areas.
How the person self-identifies : Identify a person of Hispanic American descent and interview him or her. How the person self-identifies, e.g., Mexican American, Hispanic American, Latino, etc.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd