Project operations management question

Assignment Help Project Management
Reference no: EM1343374

Project Operations Management Question

Wachovia operates a network of automated teller machines (ATMs). On average a customer withdrawals $80 of cash each time. The bank estimates that the fixed cost of filling an ATM with cash is about $100 regardless of the amount of cash put in. Each month on average 600 customers use the ATM to withdrawal cash. How much cash should the bank keep at an ATM if its annual cost of money is 10%? How often should the bank replenish an ATM?

Reference no: EM1343374

Questions Cloud

Important for successfully completing a project : The project management structure or the culture of the organization - Important for successfully completing a project
How might goals be measured for feasibility : Does the system offer adequate controls to protect against fraud and embezzlement and to guarantee the accuracy and security of data and information?
Project selection - annual earnings approximate cash flows : Suppose only one project can be chosen and the annual earnings approximate cash flows excluding finance charges, which project should be chosen?
Question about financial systems : Explain what are the economic functions financial intermediaries perform and what is the role of broker in the financial market
Project operations management question : How much cash should the bank keep at an ATM if its annual cost of money is 10% and how often should the bank replenish an ATM
Project management - managing risks : Project Management - Find some items that might go wrong during this type of project
Macro and micro project risk management : Macro and Micro project risk management - describe the difference between Macro and Micro risk management.
Equipment on an economic basis : Estimates the cost of a customers waiting time in queue in terms of future business lost to the competition to be $20 per customer per hour can she justify leasing the new equipment on an economic basis?
Who should create breakdown : Small project: Who should create breakdown - Who should create the work breakdown structure for the team and describe

Reviews

Write a Review

Project Management Questions & Answers

  Changes in company is necessary if any problems occur

What difficulties can occur if the contractors have decided on work assignments, and what changes may be necessary if problems occur?

  Fundamental trade-offs to crash a project

Describe the fundamental trade-offs made when deciding whether or not to crash a project.

  Flexibility do project managers exercise in situation

How much flexibility do project managers typically exercise in situations like this?

  Determining earliest-latest and slack times for activity

The following are activity times for the project. Find the earliest, latest, and slack times for each activity. Then Find the critical path.

  Describing consensus on the scope of project

Discuss and come to a consensus on the scope of the project, including the major deliverables and the items that are not part of the scope.

  Explaining normal cash flows of project

Assume a project has normal cash flows. All else equal, which of the following statements is correct?

  Project adjustments and procurement

Project Adjustments and Procurement - Can you make a full stop on a project to make adjustments and justify your answer.

  Functions for a project manager to control schedule changes

Explain different methods and techniques a project manager could use to minimize or control changes to project schedules

  Manage risks in project management

Describe how risk has impacted a project that you have been associated with as a team member or project leader and give at least two examples where surprise events impacted the project.

  Techniques and procedures for mitigating risks

Describe appropriate techniques and procedures for mitigating risks you identified.

  Modify the integrated project plan

Modify the integrated project plan as a result of a team meeting to incorporate the changes to the plan as provided by the CBDF and the trickiest part of this assignment is to evaluate how you will do this.

  Selecting project as a risk averse investor

Assume the risk-free rate of return is 2% and the market risk premium is 8%. If you are a risk averse investor, which project should you choose?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd