Project managementassume that an activity has a normal tune

Assignment Help Project Management
Reference no: EM13363193

Project Management

Assume that an activity has a normal tune of 20 weeks, a normal cost of $72,000, a crash time of 16 weeks, and a crash cost of $100,000. By how many weeks, at most, can this activity's duration be reduced? What is the cost per week to accelerate this activity?

Reference no: EM13363193

Questions Cloud

Modify the integrated project plansome changes to your : modify the integrated project plansome changes to your program. discuss and begin to prepare plans among your group
Entertainment due to electrical code changes all the : entertainment due to electrical code changes all the equipment that bands bring to the stage will need to be checked by
Integrated project planmerchants for the first time in : integrated project planmerchants for the first time in history the festival can sell beer. limit 2 per person per day.
Risk management identifying risksrisk management is a : risk management identifying risksrisk management is a matter of identifying the situations that could cause your
Project managementassume that an activity has a normal tune : project managementassume that an activity has a normal tune of 20 weeks a normal cost of 72000 a crash time of 16 weeks
Project risks1 consider you are the project manager of a : project risks1. consider you are the project manager of a team of software specialists working on a project to produce
Terminal cash flows at end of the projectjohnson corp is : terminal cash flows at end of the projectjohnson corp. is considering a huge project to expand.the project has an
Scheduling the waitstaff for a 24-hour restaurantyou are in : scheduling the waitstaff for a 24-hour restaurantyou are in charge of scheduling the waitstaff for a 24-hour
Discuss about article obama administration criticizes : discuss about article obama administration criticizes jpmorgan over mortgagesthe article i chose this week obama

Reviews

Write a Review

Project Management Questions & Answers

  Project planning - breakdown structure and control

Show what controlling measures should be taken during the planning phase and then provide a generic method for creating a project schedule starting with the creation of the work breakdown structure.

  Project scope driversa what were the project drivers in

project scope driversa. what were the project drivers in terms of problems and opportunities and go beyond what is

  Using project risk managementplease just pick one topic

using project risk managementplease just pick one topic below and use project risk management plan point to develop the

  Explain the different types of project feasibility factors

Explain the different types of project feasibility factors and list and show the different types of project feasibility factors

  Show the project scope statement

Explain how do you see the Project Charter content feeding into the Project Scope Statement?

  Explaining high-visibility project

In spite of their poor cost performance, why do you think these projects were supported to their conclusion? What would it take to kill a high-visibility project such as these?

  Due to a down-turn in the economy

Due to a down-turn in the economy, your company has been experiencing financial losses in revenue. You have been asked to put together a team that will find 3-5 low-cost or no-cost ways to resource costs by 25% for your company's main product line

  Equipment on an economic basis

Estimates the cost of a customers waiting time in queue in terms of future business lost to the competition to be $20 per customer per hour can she justify leasing the new equipment on an economic basis?

  Project scope and schedule for wal-mart

How would a consultant develop the project scope and schedule for Wal-mart?

  Project evaluation using the marr

You are curious as to how long you should keep the car and you will graduate soon and you do not want to keep the car longer than 4 years.

  Describing how to estimate effort

Describe how to estimate effort. Discuss why it is so important to estimate projects correctly.

  Cultural norms affect project from a positive perspective

How did the cultural norms affect this project from a positive or negative perspective?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd