Project Management: Questions

Throughout a project, the Cost Performance Index has decreased from 1.3 to 0.8. The cost performance on this project has:

a. Improved.
b. Deteriorated.
c. Stayed about the same.
d. There is insufficient information to answer the question.

Question
Which of the following statements best describes the relationship between project cost and quality?

a. Six Sigma method has no relationship to project cost management.
b. Improved quality results in higher total life cycle cost.
c. Quality should be planned into the project to reduce total life cycle cost.
d. Quality is primarily a manufacturing issue and has no impact on project cost.

Question
If cumulative PV = ?100,000, cumulative EV = ?98,000, and cumulative AC = ?104,000, the project is:

a. Ahead of schedule.
b. Operating below project cost projections.
c. Likely to come in over budget at completion.
d. Likely to come in under budget at completion.

Question

Which of the following methods is most likely to result in an increase in project cost?

a. Earned value method
b. Trade-off decisions involving resources, schedule, and performance
c. Resource leveling
d. Crashing activities to meet end dates

Question

In which type of cost estimating is regression analysis technique used?

a. Bottom-up
b. Definitive
c. Parametric
d. Engineering (grass roots)

Reference no: EM13363479

Questions Cloud

Traits of effective and ineffective managermanager : traits of effective and ineffective managermanager effectivenessintroductionextensive research and evaluation was
Puropse of work breakdown structure wbs1 paul mali : puropse of work breakdown structure wbs1. paul mali management by objective new york john wiley 1972 p. 12 defines mbo
Develop a schedule for introducing a new product1you just : develop a schedule for introducing a new product1.you just have been instructed to develop a schedule for introducing a
Problem definitionrural areas do not have proper internet : problem definitionrural areas do not have proper internet access and are unable to manage downloading anything. certain
Project management questionsthroughout a project the cost : project management questionsthroughout a project the cost performance index has decreased from 1.3 to 0.8. the cost
Calculation of net cash flowgarfield inc is considering a : calculation of net cash flowgarfield inc. is considering a thirteen year investment project with forecasted cash
Project managementa what is the definition of a project : project managementa. what is the definition of a project? what are some of the elements that differentiate a project
Expected benefits that are motivating the : expected benefits that are motivating the organizationbriefly explain the organization that is in need of the pool.
1 implement the tronomino tiling algorithm your program : 1. implement the tronomino tiling algorithm. your program should take an arbitrary input positive integer k in the

Reviews

Write a Review

Project Management Questions & Answers

  Developing policy for reducing the hazard-incident

Develop a policy that is specific for reducing the hazard/incident.

  Operation budgeting

How much was the rate variance and based on the above, how would you rate the head housekeeper, considering the dollars spent? Use figured to support your answer.

  Strengths and weaknesses of different perspectives

Analyze the relative strengths and weaknesses of the different perspectives for developing operations strategy :the top-down and the bottom-up.

  How many of you are involved in the reporting aspect of a

how many of you are involved in the reporting aspect of a projectprogram or operation? do you agree with the methods

  Explain what degree of risk do you believe

Explain what degree of risk do you believe should be taken for a project and should there be a % cap rate, or bottom line value, or what?

  Process of control schedule and control cost

Process of control schedule and control cost - implement the process of control schedule and control cost. You must state your case and supporting evidence for the need of implementing the process of control schedule and control cost to your stakeh..

  Schedule and cost control presentationprepare a

schedule and cost control presentationprepare a presentation comparing several different project management models such

  What items need to be addressed in defining the scope

The project scope describes what will be delivered as part of the project, and in some ways, it can be likened to the term vision.

  Show the teams progress on your project

What are some sources of barriers to group effectiveness that this group may face in trying to meet its goals and show the teams progress on your project.

  Question related to project plan forecast

Question about Project plan forecast - Describe a communication plan;explaining how progress will be reported

  Show the knowledge of the sdlc

What's the appropriate level and kinds of advice about the Systems Development Life Cycle are appropriate to give to the aspiring Project manager?

  What projects should be selected and why

Project selection - What projects should be selected and why

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd