Project Management Question and Answer

The usual purpose of the ________ scheduling heuristic is to delay cash outflows as long as possible.

Minimum slack first
Shortest task first
Most successors
As late as possible

Monitoring, as an activity, should be kept distinct from ________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

Auditing
Controlling
Evaluation
Verifying

Monitoring, as an activity, should be kept distinct from ________, which is the process of making judgments about the quality and effectiveness of project performance.

Planning
Controlling
Evaluation
Estimating

Secondary uses for monitoring include ________.

Auditing, learning from experience, and reporting progress and status
Exercising effective control over the project
Evaluating current status of the project
Fixing the blame when things go wrong

The key feature of cybernetic control systems is ________.

Manual operation
Directional controls
Automatic operation
Semi-automatic operation

In a cybernetic control system using a negative feedback loop, the speed or force with which the control operates is, in general, ________ to the size of the deviation from standard.

Disproportional
Proportional
Reciprocal
Double

Reference no: EM1343462

Questions Cloud

Difference between primary and secondary research : Explain why you chose the criteria you chose and describe the difference between primary and secondary research.
Stocked in addition to the food : In what ways is quality, or lack of quality, visible and what items must be stocked in addition to the food?
Project management control issues : Can you help answer the question: Identify project management control issues and Project Management Control Issues
Explain the organization chart of finance function : Explain the organization chart of finance function in a typical organization. What is  the key function of each role/position? Explain the difference between the  treasury and controller function.
Project management question and answer : Which is the process of making judgments about the quality and effectiveness of project performance
What can project manager do in case like this : Who may not have decision-making authority but are "warm bodies" just sent to sit in on meetings and what can the project manager do in this case?
Strategic considerations to justify a project : Strategic Considerations To Justify A Project - Many financial analysts are very skeptical of the use of strategic considerations to justify a project.
Explain the steps in the statistical analysis : Explain the steps in the statistical analysis and explain the steps in the statistical analysis
What will be this value in si units : The density of mercury is 13.595 g cm -3  . What will be this value in SI units? Give the SI units and their symbols for the following physical quantities:

Reviews

Write a Review

Project Management Questions & Answers

  Alternatives-project organization can use to respond to risk

What are the four alternatives a project organization can adopt in deciding how to address and respond to its risks?

  Developing a cost analysis of items of library project

Develop a cost analysis of the above items relating to the library project so we have hard numbers to work with and have a monetary value for reporting and audit purposes.

  Functional and dysfunctional conflict on a project

What is the difference between functional and dysfunctional conflict on a project?

  Time cash flows-terminal cash flow with ending tthe project

What is the one time cash flows/terminal cash flow associated with ending the project?

  What is the critical path when normal activities are used

What is the critical path when normal activities are used and evaluate the minimum total direct cost for each of the following project durations

  Importance of data collection in project management

By gathering data as work is executed, project managers can make decisions before the project is over and performance is presented to stakeholders

  Technique better aligns to workplace

Which technique better aligns to your workplace? Why?

  Computer production planning by linear programming

Help the computer manufacturer formulate and solve a linear programming spreadsheet model to find the production schedule that minimizes total cost over the given planning horizon.

  What can project manager do in case like this

Who may not have decision-making authority but are "warm bodies" just sent to sit in on meetings and what can the project manager do in this case?

  Responding to risk - four alternatives

Describe what are the four alternatives a project organization can adopt in deciding how to address and respond to its risks

  Cost analysis of economic development project

What factors are considered in the cost analysis of an economic development project in city/county government?

  Show the teams progress on your project

What are some sources of barriers to group effectiveness that this group may face in trying to meet its goals and show the teams progress on your project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd