Describe the connection between Project Management and an organization's Strategic Plan.
Briefly describe the task decision making responsibilities under the three project management matrix structures.
In project management terms, what is meant by "managing the trade-offs?"
What is a Project Priority Matrix and how would you use one?
Under what conditions would the bottom-up approach to estimating project times and costs be the best choice?
What is a Responsibility Matrix and how would it be used in project management?
"The best way to improve estimates is to collect and archive data on past project estimates and actuals." Agree or disagree and support your answer.
What is total slack and how do you determine it?
Identify and briefly describe the four major methods of bottom-up estimating.
In the network computation process what is a forward pass and what three things does it determine?