Project breakdown will vary in level of detail depending on

Assignment Help Operation Management
Reference no: EM132119968

1) In preparing an estimate, which of the following is not an element of the project general overhead:

a. Home office rent

b. Office supplies

c. Site offices

d. Office staff salaries

2) The estimator’s checklists and project breakdown will vary in its level of detail depending on:

a. The type and complexity of the project

b. The amount of time allowed to complete the project

c. The architect’s opinion

d. The owner’s financial capabilities

3) When preparing a cost estimate, the contractor will need all but one of the following:

a. Subcontractor’s bids

b. Unit costs

c. Working drawings and specifications

d. Change order

4) For each construction project, the estimator must consider all of the following factors before starting the estimating process except:

a. Project duration

b. Productivity of crew

c. Addition of overheads and profit

d. A building permit

5) In preparing an estimate, the sources of cost data include:

a. Historical data

b. Information provided by others

c. a & b

d. Neither a nor b

6) Communication problems can stem from the following locational difficulty:

a. Remoteness

b. Confined sites

c. Design considerations

d. Vandalism and site security

7) A project cost estimate includes the following items:

a. Direct cost

b. Indirect cost

c. Markups

d. All of the above

8) The concept of variability in cost estimating is initiated because:

a. A construction project has several stakeholders

b. The final costs of a construction project and its general requirements are dictated by many factors

c. Construction projects have different designs

d. If identical drawings and specifications is given to 100 different estimators, 100 different cost estimates will be created

9) “Fine tuning estimate" means:

a. Breaking down the project into measurable items

b. Adding the cost items of an estimate to find the total project cost estimate

c. Collecting the required data to calculate the cost of a project

d. Modification of the initial estimating selection by an estimator and then selecting the most likely value of an estimate

10) The cost alterations made by an estimator to account for profit and contingencies are:

a. Liquidated damages

b. Construction costs

c. Markups

d. Insurance

Reference no: EM132119968

Questions Cloud

Transformational leadership and transactional leadership : How does charismatic leadership come together with transformational leadership and transactional leadership?
Integrity play into the environment of validity in research : How does confidence and integrity play into the environment of validity in research? Can you have one without the other?
Pursues different business-level strategy : What are the advantages and disadvantages of acquiring a firm that pursues a different business-level strategy?
Examples of deliverables on the three goals : Looking for examples of deliverables on the three goals
Project breakdown will vary in level of detail depending on : The estimator’s checklists and project breakdown will vary in its level of detail depending on:
Element of the project general overhead : In preparing an estimate, which of the following is not an element of the project general overhead:
Are social business initiatives beneficial : Are "social business" initiatives beneficial or not to a business?
Demonstrating considerable intragroup conflict : As a manager, if your workgroup is demonstrating considerable intragroup conflict, what would you do, and why?
Continue to offer product or service : One of the things a managerial accountant can help with the decisions for is whether or not to continue to offer a product or service.

Reviews

Write a Review

Operation Management Questions & Answers

  What actions would you take from perspective of large firm

Assume you are the manager of a small firm that is dependent on a large manufacturing customer that uses the resource-dependence perspective. Put yourself in the position of the small firm, and describe what actions you would take to survive and succ..

  What is the expected number of times

Assume that customers arrive completely randomly, one at a time, at the rate of 15 per hour. Calculate the operating characteristics of interest to the manager.

  Does clark have any sources of power

To what degree were Clark's methods of influencing board members the most effective possible under the circumstances presented in the case? 3. Do you think her methods of getting things doen at the foundation were ethical? Why or why not?

  Who accepts the greatest risk under each type of contract

Why does the President want to reduce Cost-reimbursement contracts? Why is it preferred to use a Firm Fixed type contract?

  What it means by development of hard infrastructure

What it means by development of hard infrastructure. Acceleration of the digital economy

  Flowers produce the nectar which is collected by the bees

In the Sweet? Action! supply? chain, the flowers produce the nectar which is collected by the bees.

  Define high-performance work systems

Define high-performance work systems and provide four examples of HR practices that promote this performance.

  What would be the marginal revenue

Jim’s Burgers produces 600 burgers per week. Each burger sells for $3. Goody Candy orders 500 burgers for its upcoming office party from Jim’s Burgers. Jim decided to accept the order for $1250 lump sum. What would be the marginal revenue p

  What leadership attributes does this person exhibit

How does this person make you feel when you are involved with this person? What leadership attributes does this person exhibit?

  Policies inhibit the effectiveness of companies strategies

What attitudes and policies inhibit the effectiveness of companies strategies for hiring older worker? What strategies can management implement in the workplace to avoid being stereo typed or discrimination?

  Does this mean that the asset has negative risk

Why would anyone ever invest in an asset that has an expected and required return that is negative? Explain.

  Efficiency and effectiveness of project management

Develop a Matrix that is based on 4 specific categories: Explain the appropriateness of this matrix and elaborate on its contribution to the efficiency and effectiveness of project management.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd