Project ahead of schedule or behind schedule

Assignment Help Project Management
Reference no: EM131969230

You are completing a software development project. This project is expected to add SIX new features to a popular software program you sell to customers. The projected cost for the project is $100,000 and the development is expected to take 5 weeks. At the end of the second week, you spent $17,500 per new software feature and you completed the development of two new features. You are about to start the development of the third new software feature. Based on this information, fill in the table below:

BAC

PV

EV

AC

CV = EV-AC

SV = EV - PV

CPI = EV/AC

SPI = EV/PV

EAC = BAC/CPI

ETC = EAC-AC

VAC = BAC-EAC

TCPI (Cost) = (BAC-EV)/(BAC-AC)

Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?

Reference no: EM131969230

Questions Cloud

Project management and the project managers : Why are the five levels of maturity (initial process, structured process and standards, organizational standards and institutionalized process
Type of organization : Do you believe that it is more expensive to run a world-class PMO than to run another type of organization?
Determine the ratio of liabilities to stockholders equity : Ratio of Liabilities to Stockholders' Equity and Ratio of Fixed Assets. Determine the ratio of liabilities to stockholders' equity for both companies.
What is the critical path : Given the following table, how many months does it take to complete the project according to the critical path analysis? What is the critical path(s)?
Project ahead of schedule or behind schedule : Based on the values you computed, is the project ahead of schedule or behind schedule? Will the project be completed under budget or will it exceed the budget?
What amount is characterized as ordinary income : Assume Raquel sells the furniture for $75,000. What amount is characterized as ordinary income (or ordinary loss) for Raquel from this transaction?
Customer at controlling project changes : What is the role of the project client, sponsor, or customer at controlling project changes?
What is company organizational structure : Assume you are a project manager in your organization. What is your company's organizational structure?
Describe how the project manager can eliminate problems : Describe how the project manager can eliminate problems during the integration.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd