Assignment : Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation.
Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
Leadership style of gordon bethune
: What are some similarities between the leadership style of Gordon Bethune
|
Selection of a new healthcare information system
: One of the biggest decisions that any healthcare organization can make today is the selection of a new healthcare information system.
|
Evaluate the remote access infrastructure
: Evaluate the remote access infrastructure, identify vulnerabilities and suggest security improvements to mitigate risks to remote access.
|
Organization design of multi-business organizations
: In 3-4 pages discuss strategy and organization design of multi-business organizations, the mixed-model approach.
|
Production warehouse move project
: You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
|
Calculate the earnings per share for national computers
: Michelle Townsend owns stock in National Computers. Based on information in its annual report, National Computers reported after-tax earnings of $9,700,000.
|
What is the amount of the increase
: Analysts that follow JPMorgan Chase, one of the nation's largest providers of financial services, estimate that the corporation's earnings per share.
|
What suggestions for software development would you suggest
: Given this environment, what suggestions for secure software development best practices would you suggest to improve software security?
|
Find best number of batches of each candy bar to produce
: A candy manufacturer makes one type of candy bar but in two sizes, small-large. Find best number of batches of each candy bar to produce. What is maximum profit
|