Produce an activity on arrow network for the project

Assignment Help Computer Engineering
Reference no: EM133127072

Managing a Professional Engineering Project

NETWORK ANALYSIS

Question 1. Draw an "activity on arrow" and an "activity on node" diagram for each of the following situations:
a. Task K depends on Task A and Task B.
b. Task K and Task L depend on Task A and Task B.
c. Task K depends on Tasks A and B and Task L depends only on Task B.
d. Task K depends only on Task A, but Task L depends on both Tasks A and B.
e. Task K depends on Task A and C and Task L depends on Task B and C.

Question 2. Draw "activity on arrow" and "activity on node" diagrams to show the following.
Coffee is made by pouring water which has just been boiled through a charged filter.
Milk is heated and added to the filtered coffee and the resulting white coffee is served. Assume that initially both the water and the milk are cold and that the filter is charged. Use the following activities:
A - Boil water
B - Heat milk
C - Pour water through filter
D - Remove filter
E - Add milk to coffee
F - Serve white coffee

Question 3. A pattern of trenches has to be planned, marked out, dig and filled with concrete made from dry ingredients which are to be collected in the correct quantities from another location. The activities involved together with their duration and manpower are as follows:

Reference

Activity

Duration (hours)

Men

A

Plan layout

2

1

B

Mark out site

1

2

C

Dig trenches

3

3

D

Obtain concrete material

4

1

E

Mix concrete

1

2

F

Fill trenches

1

3

a. Draw an "activity on arrow" and an "activity on node" network of the project and determine the critical path and minimum time it will take to complete the project.
b. Construct a bar chart and determine the manpower requirements throughout the project.
c. Assuming that the digging equipment was taken in error by the vehicle collecting the concrete material. Draw another "activity on arrow" diagram to show the affect this would have on the completion of the project.

Question 4. A vehicle is to be inspected and then have its engine replaced. The new engine must be ordered and transport arranged to collect it from the stores section. The same transport must then be used to return the old engine, provided it has been drained and packed, to the stores section. A receipt document is required to certify the return of the old engine which must then be combined with the job card certifying completion of the fitting of the new engine before the vehicle will be accepted for out-inspection. The main activities and their durations are:

Serial

Activity

Duration (hours)

A

In Inspection

2

B

Order new engine

1

C

Arrange transport to collect new engine

2

D

Remove old engine

6

E

Collect new engine

2

F

Drain and pack old engine

3

G

Fit new engine

6

H

Transport old engine and collect receipt

2

I

Assemble documentation

1

J

Out inspection

3

 

1931_Managing a Professional Engineering Project.jpg

 

Complete the network below and determine:
a. The earliest time for completion of the project. Show total float where applicable.
b. The critical path and activities.
Redraw the network to show the effect of extending the time to arrange transport for the new engine to five hours.
Note: The network can be selected, copied and pasted into Microsoft Paint for the values to be added.

Question 5. A gantry is to be built on the side of a steep hill as shown below.

948_Managing a Professional Engineering Project1.jpg

 

a. After installing foundations for the identical towers A and B, a plinth has to be erected for tower B to compensate for the hill slope. On completion of the plinth a sighting is taken from its top to determine the height of base to be constructed for tower A to ensure final levelling. The foot of each tower is clamped in position by a series of securing plates fitted to base A and the plinth.
b. The activities to be considered with their estimated duration and manpower requirements are:

Serial

Activity

Duration (days)

Men

A

Mark out site

1

3

B

Dig foundation A

2

4

C

Concrete foundation A

1

2

D

Build base A

1

2

E

Fit securing plates for A

1

2

F

Erect tower A

3

3

G

Dig foundation B

4

4

H

Concrete foundation B

3

2

I

Erect Plinth

2

4

J

Fit securing plates for B

1

2

K

Erect tower B

3

3

L

Erect span

1

4

c. Produce an "activity on arrow" network for the project identifying the critical path and determine the minimum duration of the project in days. Show total float and free float on your network.
d. Produce a tabulated, job oriented, analysis of the network
e. Produce a bar chart representation of the network and a resource diagram for the project.
f. What will be the effect if the digging of foundation A (activity B) was extended to
i. 6 Days
ii. 8 days

If the maximum number of men available on any day was six, could the project be completed in the minimum time determined in part d assuming the digging of foundation A took the two days scheduled.

Attachment:- Network Analysis.rar

Reference no: EM133127072

Questions Cloud

Concepts of ethics and sustainability : Discuss the potential impact that consideration of ethics and/or sustainability would have had on the conduct of the project and on its deliverables
The producer of television show-we have marketing problem : The producer of a television show: We have a marketing problem. The program's ratings are low. We need to learn how we can improve our ratings.
Calculate the costs for land, building, land improvement : Calculate the costs for land, building, land improvement, machine and equipment for Munirah Bhd for year 2021 based on MFRS 116 Property, Plant and Equipment
Flow of factor incomes : 1. National income is measured as a flow of factor incomes.
Produce an activity on arrow network for the project : Produce an activity on arrow network for the project identifying the critical path and determine the minimum duration of the project in days
Do not call registry : How would you address people's doubts about whether pollsters may contact households listed on the Do Not Call Registry?
What is the equity component on January : The grant is conditional upon the completion of three years after the vesting date. What is the equity component on January
Average fixed cost of producing 2 units of output : Use the information in the table below to determine the average fixed cost of producing 2 units of output.
Currency of country a appreciated relative : (a) During 2021, the one-year interest rate in Country A increased by 1%, while that in Country B remained unchanged;

Reviews

Write a Review

Computer Engineering Questions & Answers

  Should internet access providers or telephone companies be

should internet access providers or telephone companies be allowed to monitor how you use your internet or telephone

  Write the r command to produce a table with the same row

Write the R command to produce a table with the same row and column headings, but the entries are the average temperature for that month and year.

  Explain an example of syntactic ambiguity not found

Give and explain an example of lexical ambiguity not found in this chapter. Give and explain an example of syntactic ambiguity not found in this chapter.

  Determine the height of the triangle

Write a nested loop to create a triangle that utilizes a random number between 1 and 5 to determine the height of the triangle.

  There are five factors to consider when assessing the

there are five factors to consider when assessing the growing impact of it in business firms both today and over the

  What are the the three characteristics of big data

What are the the three characteristics of Big Data, and what are the main considerations in processing Big Data? Content: Answer is complete; sufficient detail.

  Write a program that converts from twenty four-hour notation

Write a program that converts from 24-hour notation to 12-hour notation. For example, it should convert 14:25 to 2:25 P.M. The input is given as two integers.

  Develop a checklist for assessing the physical security

Physical security is a necessity in comprehensive information security. Develop a checklist for assessing the physical security of an organization.

  What will the host do with the packet

The replay window spans from 200 to 263. What will the host do with the packet? What is the window span after this event?

  What is the maximum theoretical downstream rate

What is the maximum theoretical downstream rate in Mbps of an ADSL modem?

  What new features are enabled by the memories

What new features are enabled by these memories? More broadly,describe what the two technologies (of the three above ) that you've picked are, and how they fitinto the existing memory landscape of FLASH, SRAM, DRAM, etc.

  Describe the reasons of accessing the internet

On the discussion forum, please describe the reasons for having a totally anonymous means of accessing the internet. Please also discuss the dangers.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd