Produce a take-off that details the estimated costs

Assignment Help Project Management
Reference no: EM133126979

Assessment Task: Estimate a Project

Performance Objective
The learner is required to demonstrate their ability to establish the estimated costs associated with the acquisition of materials and labour on building and construction sites, together with the application of relevant overhead costs and margins.

Assessment Description
You are required to produce a take-off that details the estimated costs including materials, labour and plant and equipment for a given project. You will also be required to apply relevant overhead costs and margins to your estimate.

Resource Requirements
Refer to your chosen project ,the Knox Bridge,ortheGlen Iris house for all the Tender details
Submission Details
You are required to submit the following:
• A completed spread sheet using Microsoft Project or similar divided into the various stages of the project which should include;
• Demolition
• Earthworks
• Drainage
• Concrete
• Steel
• Depending on your project i.e for the bridge you would have to include;
• Traffic control/Relocation of services,and permits for same/OH&S compliance issues/new guttering and footpath works/Bitumen work etc.
• For the Glen Iris house project the stages would include
• Timber frame/Trusses
• Brickwork/Concrete tiles for roof
• Windows and Doors
• Plaster work and Tiles
• Fixing and Fitout

• Completed summary that includes the cost of each part, the calculated overhead recovery rate, profit margin and GST.
Use the take-off sheets provided to record the information for each section of the estimate.
Fill out the project details on each sheet and a title. Show all of your working. Use the provided rates and prices to do your costing.
You should ensure you save your work as you progress through the questions and backup your work in a safe place.
When you have completed your take-off, submit your assessment to your trainer via "Assessment Task 3: Estimate a Project" page on the Box Hill Institute StudentWeb.

The assessment task is due on the date specified by your assessor. Any variations to this arrangement must be approved in writing by your assessor.

Scenario
You have been asked to produce an estimate and provide a quote to construct a three bedroomweatherboard home with a Colorbond roof.
You are required to read and interpret the project plans so as to be able tointerpret measurements and calculate quantities and costs, identify materials required for the project, gather information about material supply and plan and allocate human resources.
The client will be providing the following things:
• Kitchen
• Built-in robes
You will be receiving estimates for the electrical and plumbing from your regular electrician and plumber.
All prices for material and labour are excluding GST
For each of the sections listed below you are required to provide costing information that includes:
• all up price for the eachsection
• labour required and how many days or hours they are required onsite
• list of required materials
The following parts are to be estimated
• Preliminaries
• Earthworks
• Framing
• Lock-up
• Fixing
• Prime cost items
• Finish
Project Documentation
• Site plan
• Floor plans and elevations
• Sub-floor layout
• Extract from Cordels Cost Guide

Part 1 - Preliminaries
You are required to estimate the preliminary costs of this project.
Study the plans and specifications including the site plan to determine what will be required to get the project started and set up the site.
Use the pages extracted from the Cordels cost guide.

Part 2 - Earthworks
You are required to cost the earthworks for this project.
The earthworks should include the cost to excavate and pour the pad footings and install the stumps.
Use the drawings provided, the specifications below and the Ace Drilling price list located on the following page.

Item

Size

Price

Labour

hour

$40.00

Concrete

20 MPa

$185.00m3

Stumps

125 x 125mm Cypress

$15.00 L/m

Part 3- Framing
You are required to cost the subfloor and wall framing using the provided drawings and specifications below.
To cost the supply and installation of the roof trusses use the provided drawings and the unit price below.

Item

Size

Price

Labour

hour

$40.00

Sub-Floor

Ant Caps

Full caps 230mm x 230mm

$2.10 each

Bearers

130 x 63 LVL H2 Treated

$13.65 L/m

Joists

90 x 45 LVL H2 Treated

@ 450mm centres

$6.75 L/m

Gun nails

75mm x 3.1mm

$64.00 box

Particleboard flooring

3600 x 900 x 18mm

$35.00 per sheet

Liquid Nails

Tube

$3.65

Wall Framing

Plates

90 x 45 MGP 10 Pine

$3.95L/m

Common studs

90 x 35 MGP 10 Pine

@ 450mm centres

$2.95L/m

Jamb studs

90 x 45 MGP 10 Pine

$3.95L/m

Noggings

90 x 35 MGP 10 Pine

$2.95L/m

Trimmers

90 x 35 MGP 10 Pine

$2.95L/m

Lintels

190 x 45 MGP 10 Pine

$8.50L/m

Beams

240 x 45 MGP 12 Pine

$15.50L/m

Bracing

 

 

Hoop iron

30x0.8mmx30m

$67.21 per roll

Tensioners

Pack of 10

$29.50

Structural clouts

2.8 x 30mm 2kg box

$18.16 box

Ply Brace

900 x 2400mm

$16.95 per sheet

Gun nails

75mm x 3.1mm

$64.00 box

Roof Framing Unit Rates

Item

Rate

Trusses (Calculated on flat plan; outer line of overhang)

$48.97 m2

Roof Battens 70 x 45 MGP 10 @ 900mm centres

$5.71L/m

Record on your take-off sheet the amount of labour required and the time required onsite to complete the roof trusses and battens.

Part 4 - Lock-up
Weatherboards
You are required to price the supply and installation of the Hardi plank weather boards using the drawings provided and the specifications below.

Item

Size

Price

Labour

hour

$40.00

Woodgrain Hardiplank 300mm

300mm x 4200mm, 280mm effective cover

$29.41 per length

Nails

50 x 2.8mm galvanised nails 2kg

$19.95 per box

End stops

70 x 30 TP

$3.20 L/m

Bradford EnviroSeal Wall Breather Foil

1350mm x 20m - 27m2

$52.30 roll

 

1350mm x 60m - 81m2

$161.37 roll

Foil Fasteners

500 per box

$19.00

FlashingsAlcor Std

150mmx30M

$70.30 roll


Lock-up Carpenter
You are required to cost the supply and installation of the windows, fascia, eavesand the laundry door using the provided drawings and the specifications below. You are also required to price the installation of the shower tray and frame and install the bath.

Item

Size

Price

Labour

hour

$40.00

Windows

various

$3,650.00 (All windows)

FlashingsAlcor Std

150mmx30M

$70.30 roll

Nails for windows and door jamb

75mm x 3.15mm Galv. Bullet Head Nails - 2kg

$19.95 box

laundry door

2040 x 820 x 25 obscure glass

$308.00

laundry door jamb

140 X 31 H3 Pine Jamb Rebated Primed

$68.80/ 5.4m

Lock set

Entrance Set Spartan Satin SS - ITW Proline

$48.68

Hinges

100 x 50mm

$3.50 each

Gun nails

75mm x 3.1mm

$64.00 box

Fascia

190 x 25mm

$12.50 L/m

Eaves framing

70 x 35 F5

$2.55 L/m

Quad

19 x 19mm

$2.30 L/m

Hardiflex

450 x 2400 x 4.5mm

$11.50 per sheet

Fibro nails

25mm x 2.0mm Galvanised - 500g

$6.30 box

Mortar mix

20kg bag

$12.40 bag

Colorbond Roofing
Use the unit rates provided to cost the supply and installation of the Colorbond roofing and required flashings,

Item

Rate

Quad gutter 125mm

$33.20 per L/m

Gutter stop ends

$11.34 each

Downpipes

$31.41 per L/m

Glasswool Blanket

$10.90 per m2

Colorbond roof sheeting

$28.31 per m2

Barge capping

$14.54 per L/m

Ridge capping

$18.36 per L/m

Record on your take-off sheet the amount of labour required and the time required onsite to install the guttering, Colorbond roofing and required flashings.

Part 5 - Fix

Plasterboard
Using the rate provided calculate the cost of plastering this project. Supply, hang, set and sand 10mm Plasterboard.

Item

Rate

Walls

$26.39m2

Ceilings

$29.79m2

Cornice

$9.79/m

Make a list of the required screws, adhesive, tape and setting compound.
Record on your take-off sheet the amount of labour required and the time required onsite to complete the plastering.
Using the rate provided calculate the cost of supplying and installing bulk insulation.

Item

Size

Price

Labour

hour

$40.00

Wall Batts

R2.0 Coverage per pack 16m2

$69.00

Ceiling Batts

R5.0 Coverage per pack 5.5m2

$68.00

Doors, Skirting & Architraves
Price the supply and installation of the internal doors, door hardware, skirtings and architraves using the provided drawings and the specification below.

Item

Size

Price

Labour

hour

$40.00

Jambs

110 x 19mm @ 5.4m

$32.50 each

Jamb nails

60 x 2.8mm bullethead 1kg

$13.60 box

Internal doors

Readicote

 

 

620mm

$48.11

 

720mm

$48.11

 

820mm

$48.11

Cavity slider

Ezi-Slide Door 2040 x 720 x 90mm

$143.02

Flush pull

115mm x 2 - ITW Proline

$14.63

Passage set

Passage Set Bala ABZ - ITW Proline

$21.85

Privacy set

Privacy Set Bala ABZ - ITW Proline

$23.00

Hinges

88mm

$0.95 each

Fixing Nails

45mm Brads

$35.00 box

Architraves

Bullnose Architrave - FJ Pine68 x 11mm

$1.85 L/m

Skirting

Bullnose Architrave - FJ Pine92 x 18mm

$4.70 L/m

Part 6 - Prime Cost Items
You are required to cost the supply of the prime cost items listed below. You must research your own prices.
• Bath
• Toilet
• Vanity
• Shower tray

Part 7 - Finish
Paint
Use the provided drawings and the unit rates below to cost the painting for this project

Item

Rate

Internal walls

$15.60 per m2

Internal ceilings

$21.00 per m2

Doors

$24.70 per m2

External fibrecement walls

$10.59 per m2

External fibrecement ceilings

$14.19 per m2

Record on your take-off sheet the amount of labour required and the time required onsite to complete the plastering.
List in litres the amount of paint required to complete each section of painting.
Tiles
Use the drawings provided and the unit rate below to estimate the labour for wall and floor tiling. The following areas will be tiled:

Room

Details

Bathroom

 

Walls

1 tile high skirting

Shower wall up to 1.8m

2 tile high splash back above vanity

Floor

Entire bathroom floor

Kitchen

 

Walls

600mm splash back above sink

Floor

Entire kitchen floor

Record on your take-off sheet the amount of labour required and the time required onsite to complete the tiling

Clean
You are required to cost a final site clean and final house clean. Use the provided extract from the Cordels cost guide to estimate a price.

Part 8- Margins

You are required to calculate the margin required to recover the business overheads.Use the data below to calculate the margin.

Overheads

Items

Cost

Premises

Rates

$110.00

 

Electricity

$256.00

 

Water

$110.00

 

Telephone

$330.00

Vehicles

Lease/loan repayments

$4,300.00

 

Registration

$1,250.00

 

Insurance

$1,945.00

 

Fuel

$7,320.00

 

Maintenance

$1,060.00

Maintenance and depreciation

Office furniture

$450.00

 

Office machines and equipment

$845.00

 

Tool repairs and replacement

$1,360.00

Consumables

Stationary

$256.00

 

Postage

$60.00

 

Safety equipment , ppe

$320.00

Marketing

Advertisements, leaflets

$2,800.00

 

Website

$1,468.00

 

printing

$645.00

Subscriptions and fees

Builders registration

$180.00

 

Business name

$120.00

 

Industry associations

$580.00

 

subscriptions

$88.00

Cost of finance

Banks charges, overdraft fees

$347.00

Professional fees

Accountants

$1550.00

 

Book keeping

$4,600

 

Total Annual Overheads



Forecast Turnover
1 new home @ $265,000
4 medium size extensions @ $135,000 each project

Part 9 -Summary

Using the table below produce a summary of the cost of each section, apply the overhead margin, a profit margin of 15% and GST to the estimate.

Reference no: EM133126979

Questions Cloud

What is its break-even point in units : Maju's sales revenue was RM350,000 and its net operating income was RM25,200 for the year. What is its break-even point in units
Lao people democratic republic : In the 1994-2017 time frame, was labor's share of income higher in (i) the country you identified as being better described by the Cobb-Douglas production funct
What will be the nominal rate of return : What will be the nominal rate of return on a perpetual preferred stock with a $100 par value, a stated dividend of 8% of par
Calculate the cross-price elasticity of demand : (a) When a local cinema?increased its ticket prices from $20 to $24, there was a 30% decrease in sales for a nearby popcorn seller. Calculate the cross-price el
Produce a take-off that details the estimated costs : Demonstrate their ability to establish the estimated costs associated with the acquisition of materials and labour on building and construction sites
Determine the unknown down payment X : If the interest rate is 12% compounded monthly and the monthly payment is worth PhP 50,000, determine the unknown down payment X
Children cope with crises : The Midwest dealt with a natural disaster of flooding in 2001 and 2019. These type of disasters create vulnerability to the human population located in the disa
What would be the present capitalized value of capital lease : Estimated residual value is 0 dollars Interest rate is 8%. Given the preceding information, what would be the present capitalized value of the capital lease
How can we prevent future instances of fraud from occurring : You will be responsible for discussing your thoughts on Professor Black's TED Talk from the vantage point. How can we prevent future instances of fraud

Reviews

Write a Review

Project Management Questions & Answers

  Create a request for proposal for a wedding

Create a Request for Proposal for a wedding. You are looking for one vendor who will provide food, beverages and hotel rooms.

  What is the legal consequence

What is the legal consequence if General Contractors fails to complete the house by June 1 but does finish it by June 20?

  Management related training documentation

Make project management related training documentation - Describe each of the phases of the project management process and its related knowledge areas. List the major activities in each phase.

  How many units of petroleum will be produced

What is the effect on productivity of doubling both the units of labor and the units of capital?- how many units of petroleum will be produced?

  Resource and what are the classical kinds of resources

What is a resource and what are the classical kinds of resources? How are resources measured? Why is it not possible to summarize resources

  Develop its programme or portfolio management capability

Question: Can you providing an example of an organisation that utilises/utilised change agents as part of a major change initiative to develop its programme or portfolio management capability

  Balancing project and team skills

Explain how would you balance your efforts to get the project done with your efforts to help team members use their work on the project to develop themselves professionally?

  Lessons-learned report for skywrench

Though heroic efforts and extremely long hours, the contractor labor and employees managed to complete the move only a few days late. Complete a Lessons-Learned Report for SkyWrench. Be creative.

  Bring out the scope planning concepts

Summarise what each paper is about and how the two papers interrelate with each other, in matters of scope planning - Describe briefly the inferred scope

  External support for aircraft lease return project

Develop a specific research question regarding an aspect of the topic selected - Adopt an explicit viewpoint in regard to the formulated question

  Demonstration of how you are managing your personal scope

Demonstration of how you are managing your personal scope, cost and time plans as evidence in support of your quality plan.

  Consume only products their own nation produced

Imagine that the nations of the world were to suddenly cut off all trade with one another, and the people in each nation were able to consume only products their own nation produced. What products might you no longer be able to obtain in the U.S.? Wh..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd