Problem regarding the earned value calculation

Assignment Help Supply Chain Management
Reference no: EM13951326

Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 65% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.

Activity C is finished. It finished 2 weeks late. It cost $200,000. And it was planned to have cost $250,000.

Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

 

2. Calculate the CV, SV, CPI, and SPI for each activity and the total project.

 

3. What is your assessment of the project at this time?

Reference no: EM13951326

Questions Cloud

Challenges in the global business environment : According to the textbook, ongoing challenges in the global business environment are mostly attributed to unethical business practices, failure to embrace technology advancements, and stiff competition among
Four behavioral approaches to job design : The purpose of this document is to provide clear, succinct and detailed explanations of four behavioral approaches to job design. The four behavioral approaches to job design include: (a) job enlargement, (b) job rotation, (c) job enrichment, and ..
What is the value of the symmetric key : In the Diffie-Helman protocol, what happens is x and y have the same value, that is, Alice and Bob accidentally chosen the same number?
Operating system that allows a single : A complete operating system that works on a desktop computer, notebook computer, or mobile computing device is a operating system.
Problem regarding the earned value calculation : Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.
How much more secure is this double encryption : Now consider a double-encryption method that adds i to each plaintext character and then adds j to the resulting ciphertext character to get another ciphertext character. Again, all calculations are modulo 256.
Problem regarding the total quality management : 1. Explaining to the new leadership on how Total Quality Management (TQM) would enable the organisation to develop better business functions/operations thus achieving world class excellence.
How many 8-letters password are possible using all alphabets : Using only 26 capital letters of the alphabet, how many 8-letters password are possible?
How does resulting increase in kinetic energy compare : If twice the force is exerted over twice the distance, how does the resulting increase in kinetic energy compare with the original increase in kinetic energy?

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Supply chain network design for cwc

This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?

  Criteria when making new location decisions

Identify a number of the typical criteria used when making new location decisions

  Draw the project network

Determine the mean critical path for Brent's job search process. What is the variance of the project duration?

  Compare and contrast economic - market, and relevancy

Please compare and contrast economic, market, and relevancy value.

  Brushing up on inventory control

Health system in Pennsylvania

  Supply chain strategy

Supply chain strategy

  What is the economic order quantity for fans in units

Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.

  What factors reduce the capacity of the organization

What factors reduce the capacity of the organization to get its objectives?

  What is the total annual cost

What is the total annual cost

  Supply chain management questions

Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  How warehouses can add value in the supply chain

How warehouses can add value in the supply chain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd