A personnel manager must schedule the police force in such a way as to satisfy the staffing requirements shown in the table below
TIME
Minimum number of officers required
Midnight-4 A.M.
5
4 A.M.-8 A.M.
7
8 A.M.- Noon
15
Noon-4 P.M.
4 P.M.-8 P.M.
12
8 P.M.-Midnight
9
Shift
Starting Time
Ending Time
1
Midnight
8:00 A.M.
2
4:00 A.M.
Noon
3
4:00 P.M.
4
8:00 P.M.
6
The officers work 8-hour shifts. There are 6 such shifts each day. The starting and ending times for each shift are given in the table above. The personnel manager wants to determine how many officers should work each shift in order to minimize the total number of officers employed, while still satisfying the staffing requirements.
Formulate the problem as an integer linear programming model. (see examples on pages 267 and 279 of your textbook). Write the Objective function and the Constraints
HINTS:
To formulate the Objective function, note that the total number of officers is the sum of the number of officers assigned to each shift. The personnel manager wants to minimize this sum.
To formulate the Constraints note that officers are on duty for 2 time intervals. For example, shift 1 is on duty during the first time interval (Midnight to 4:00 A.M.). and the second time interval (4:00 A.M.-8:00 A.M.). Each time interval has two shifts of officers.
ne week for up to 100 units, two weeks for 101 to 200 units, and three weeks for 201 to 300 units also four weeks for 301 or more units.
Select one that you believe to be the most influential and explain why. Provide specific examples of one or more countries that have experienced economic growth for the factor selected.
Describe in detail the appropriate relationship between authority and responsibility in proper delegation. Concerning authority and responsibility.
You decide to take on the project of establishing consistent levels of inventory to meet customer demands. Most of your supplies are purchased from a few distributors which call on your store once every 2 weeks. describe how many boxes of paper wou..
Assuming it needs to be pulled at 5 mph, illustrate what size tool and FWAD tractor would be needed. For each working day you can average 8 hours in the field and field efficiency is 80%.
what is the name of the damages that B can recover from A to compensate B for his loss of the contracts with C, D, and E?
Describe four (4) strategies the government must address to sustain union membership also representation among public workers.
Should ethical considerations be included in analyses of an organization's internal also external environments. Explain why or explain why not.
Explain whether additional compensation might need to be offered as a result of your plan to change job designs and work measurements.
The owner of Genuine Reproductions (GR), a company that manufactures reproduction furniture, is interested in measuring inventory effectiveness
Your current equipment is fully depreciated and can produce the 2,000 units per year at a margin of only $4.00 per unit. Should you purchase the new equipment. Under illustrate what conditions.
The daughter of the owner of a local hamburger restaurant is preparing to open a new fast-food restaurant called Hasty Burgers. Based on the arrival rates at her father's outlets, she expects customers to arrive at the drive-up window according to..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd