Probability of completing the project on time

Assignment Help Project Management
Reference no: EM13320829

547/15d

If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?

Activity Expected Time Variance

A 2 0.03

B 3 0.44

C 2 0.11

D 2 0.03

E 1 0.03

F 2 0.11

G 4 0.44

H 4 0.11

I 2 0.03

Activities on critical path:  A, B, G, H, I

E(T) = 2+3+4+4+2 = 15

Variance on critical path:

σ2= 0.03 + 0.44 + 0.44 + 0.11 + 0.03 = 1.05

From Probability Distribution Table, we find 0.99 probability occurs at z = +2.33.

Thus

Doug should begin working on the project 17.4 weeks ahead.

Reference no: EM13320829

Questions Cloud

Develop a process for assembling the yard sign : Develop a process for assembling the yard sign. Assume that you use 1 stake, one pasteboard sign and staple three staples per sign. Estimate how you will organize the work, how big a single team will be, how many signs per hour to plan for, how many ..
Identify any instances of pseudoreasoning : "Identify any instances of pseudoreasoning in the following passage either by naming them or where they seem to conform to any of the patterns described in the text, by giving a brief explanation of why the pseudoreasons are irrelevant to the point a..
What is the minimum thickness it could have : Sunlight shines directly on to the wall of a large soap bubble (n = 1.33) which is floating in air (n=1). What is the minimum thickness it could have to produce completely destructive interference for blue light (%u03BB = 475 nm)
Business case and identify the business decisions : The Final Project requires you to bring into play all aspects of the course. For the Final Project you will given a brief business case to analyze. Your analysis includes three parts: an analytic section via Excel, a graphic section via PowerPoint, a..
Probability of completing the project on time : If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?
Calculate the flow rate in the pipe between the reservoirs : Two reservoirs are connected by a pipeline. The pipeline is 1 m in diameter and has a friction factor of 0.03. The elevation difference between the reservoirs is 30 m. The two reservoirs are 5 km apart.
Corporate social responsibility-conclusion-recommendation : What is this corporation's social corporate responsibility in this case for the four areas of corporate social responsibility? Based on the above, as well as what you have learned about ethical theories and foundations of moral development, what is y..
Find the direction of the magnetic force on the airplane : In a lightening bolt, current travels upward, from ground to cloud.Suppose that at the moment that a 35,000, what is the magnitude and direction of the magnetic force on the airplane
Calculate the deflection angles and chords to stations : Computations are to be made for a street curve with delfection angle delta = 50 degrees 00 minutes 00 seconds and centerline radius of 120 feet. The PI is at station 8+72.43.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd