PRJ5003 Project Constraint Management Assignment

Assignment Help Project Management
Reference no: EM132973221

PRJ5003 Project Constraint Management - Asia Pacific International College

Project Scope, Time and Cost Management

Assessment - Presentation of project plan and status to a sponsor for a project case.

This assessment is designed to assess your technical skills in analysing a project case, writing, a project status report, and communicating a project status report effectively to different stakeholders. You required to work individually.

You are required to prepare power point presentation slides that include adequate information about the project status, then you will need to present your analysis and report (verbal presentation).

Project Case Background:

Lean Construction is a general contracting company based in Sydney, Australia. The company performs general contracting work mainly in the area of construction. The company executes approximately 15-35 projects at any given time and each project is managed by a senior project manager.

Most government contracts are awarded to Lean Construction on the fixed cost basis contract and on "design-bid-build" basis procurement method. That is, Lean Construction bids on the projects after the design has been completed by the government and Lean Construction major tasks is building only. Lean Construction is not involved either directly or indirectly in any design aspects of the project.

The general contracting organisations like Lean Construction that work on the fixed cost "design-bid-build" projects can only be profitable by completing projects on time and within budget. However, in construction projects, cost and/or schedule overruns could occur due to a variety of internal and/or external factors. These costs or schedule overruns can quickly wipe out profit margins and may result in a loss. Project losses generally are the result of problems of a few activities in a project which may impact other activities and hence, the entire project may be impacted negatively. It is not possible to avoid all schedule or cost overruns (like schedule overruns due to severe weather conditions), however, proper project monitoring can reduce the impact of these overruns.

Recently Lean Construction awarded a contract by Parramatta Council in Western Sydney for building a community centre for people in Western Australia in the basis of the fixed cost "design-bid-build" projects.

Project Case Data:

The following Data are presenting the project case
Table 1: is the project Main and sub-tasks (outline WBS) Table 2: is the schedule plan baseline
Table 3: is the cost plan baseline

The Problem:

The project was planned to start on 1st of Jan. Working hours and days are 8 hours Monday to Friday. At the end of December, just two weeks before the starting of the project, a severe thunderstorm disrupted the construction site. The Project team managed to start the project on time as planned and to complete January's tasks, but more than two weeks of work time was lost from February's tasks due to the flooding of the site caused by the storm. This loss of time could not be made up by an extension of the project time. The building had a major event scheduled at the end of construction.

By the mid of March, another problem surfaced related to the quality of work performed by a sub-contractor. The foundation sub-contractor failed to meet the standards set in the contract. About 20% of the work completed in March by this sub-contractor had to be redone. This resulted in delaying some of the activities, but the project manager and the team did not update the schedule and cost baselines.

In June, the project manager realized that the sub-contractor for interior work was having problems in procuring cabinets and other specialty items. A meeting with the sub-contractor revealed that the sub-contractor was having problems with labour and finances. The project manager did not monitor the project performance and progress since the start of the project, and the project manager now is not yet sure of the problem. At this time, hiring a new contractor is not an option. The government requested a status report from the contractor. A new project manager took place of the old project manager and first thing he asked for is a status report for End of June 2021.

Requirements and supporting documents:
You are required to complete all the tasks below (1-6)

1- Assume that you developed the project plan at the time of the bidding, summarize your key aspects of your project plan (Project Scope Statement, WBS, Schedule Baseline, Cost Baseline). This means you need to create the following (A-F)
A- Complete the Project Charter and the Project Scope Statement for this Projects (Just complete the charter and PSS templates) use the information provided and complete the relevant section in the templates (make appropriate assumptions).
B- Draw a WBS for this Project (hierarchal WBS) use the excel sheet template provided during the class.
C- Create WBS dictionary for each main task and its sub-tasks (consider each main task is a Work Package).
D- Draw the project network diagram using the precedence diagram method, use CPM Analysis and find each task ESD, EFD, LSD, LFD, TF, and FF, project duration and the critical path (s). Assume F-S relationship between the tasks.
E- Establish Project schedule with Gantt chart and show ES, EF dates, Floats and the critical Path. Use the excel sheet template provided during the class or any software you are familiar with.
F- Create time phased budget for each main task only, this means for the main task A to F (A. Site Development, B. Foundations, C. Walls + Roof, D. Interiors,
E. Bathroom and Kitchen, F. Finish), use the template provided during the class.
2- Assume you are required to present a status report to Parramatta Council about your project status on end of June 2021, use the information provided and utilize Earned Value Analysis Method (EVA) to report about your project status.
3- Present what actions do you recommend to the sponsor given your findings from the EVA on end of June.
4- If any change required to the scope, schedule, and cost, complete the change request form, and explain what changes should happen and how to record it, to update baselines and to communicate it
5- Write down the lessons learned from this project.
6- Given the actual costs in previous months (Table 5) and given the percentages of completed work in previous months (Table 4), utilise EVA and determine when would the project manager have recognised that there is a problem in the project if he/ she was monitoring the project progress and performance monthly? What would you do back then if you were the project manager?

Attachment:- Project Constraint Management.rar

Reference no: EM132973221

Questions Cloud

How should nod classify the lease : Risk associated with this lease was not normal when compared with the risk of collection of other similar receivables. How should NOD classify this lease?
Defined-benefit instead of defined-contribution : Janet has been in a defined-contribution pension scheme since she was 40 and will retire in one year's time at age 66. Her salary is currently £62,000.
What is the estimated cost of the ending inventory : Patel Packing had the following information for its inventory: Sales at retail: $145,000. What is the estimated cost of the ending inventory
Type of product in the current economic market : The onset of the COVID-19 pandemic forced many companies to conduct business remotely rather than in office buildings. In many cases, these companies found it m
PRJ5003 Project Constraint Management Assignment : PRJ5003 Project Constraint Management Assignment Help and Solution, Asia Pacific International College - Assessment Writing Service
Explain the reasons for importance leadership values : 1. Identify 1-3 leadership values that are most important to you. Explain the reasons for their importance, using the below questions as a guide:
What is the current book value per share : The cost of the investment is $640,000. What is the current book value per share and the book value per share with the investment
Examine the hierarchy-of-needs : Examine the hierarchy-of-needs, two-factor, and achievement motivation theories, and assess their value to international human resource management.
What would be the amount for depreciation expense : WIN recorded the leased asset at $285,488 on January 1, 2019. What would be the amount for depreciation expense which WIN would record in 2019?

Reviews

Write a Review

Project Management Questions & Answers

  Project management - the life of a projectuse your favorite

project management - the life of a projectuse your favorite search engine for the term project management adding other

  Conduct a preliminary literature review

PPMP20015 Problem statement and Research question - Conduct a preliminary literature review and evaluate literature.

  Develop a report for the given agile project scenario

Your task assignment is to develop for this Agile project scenario four deliverables. Deliverables: individual Product Vision PowerPoint Submitted (MS PowerPoint recommended).

  Identify areas in which the project was a success

Use the provided materials to draw conclusions about the hypothetical project; identifying areas in which the project was a success and areas that could be improved.

  Project managementwhat are the differences among milestones

project managementwhat are the differences among milestones deliverables objectives and goals?what is the relationship

  Project managementcompany a works in a business environment

project managementcompany a works in a business environment of rapid and drastic change together with strong

  Buiness management

Evaluate your current or former manager on each of the five components of emotional intelligence and explain how you can apply the principles of emotional intelligence to your current situation?

  Create a time-phased budget for your example project

In scope items are list of requirements that are going to be implemented as part of this system. Out scope items are list of functions and features that are not going to be implemented in this project but can be done later for this application.

  Compare appropriate formulas and point out how they differ

When exponential smoothing is used in fitting a curve to a time series, the approach is slightly different from its application to forecasting.

  Do you have any examples and or references

Can you tell me what conditions make using three-point estimating justifiable? Do you have any examples and or references?

  Students arrive at the student services counter

Students arrive at the student services counter at an average of one every 15 minutes. Each request takes on average 12 minutes to be processed.

  Determine and explain why innovation is important

Determine and explain why innovation is important to organizations and what can happen to companies that fail to innovate

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd