PROJECT PLANNING & CONTROL Exercise -

Please print PDFs of the following reports:

Note:

Print the following Daily Bar Charts, list the activities in ES/EF sequence, show each activity happening as soon as possible, and include the float bar. Remember to make the reports look professional; organized, labeled etc. Take the time to read each report carefully and make sure the schedule looks like it should. You should be able to correct any mistakes by a careful examination of each schedule and thereby earn a high grade on this assignment.

1. A separate bar chart for each of the following:

A. Crane

B. Backhoe

C. Piledriver

D. Concrete Pump

E. Girder Supplier

F. All concrete pours

2. Overall bar chart schedule showing all activities.

3. A bar chart showing that one road will always be open, or that only one will be closed, at a time.

Note: After creating PDFs of the reports check to see if they make sense to you, Look for overlaps on equipment; if there is sufficient float so that the available equipment can be worked within the float that is ok. You can do this project under about 90 days. To ensure a high grade, make certain you carefully read the reports.

Attachment:- Assignment Files.rar

Reference no: EM131968357

Questions Cloud

Describe consumerism : Describe consumerism. Describe a specific context and explain what consumerism means in the setting.
What do competitors do better than your identified area : What do competitors do better than your identified area? What is the competition doing that may have an impact on your identified area?
Identify a strategic goal within your sphere of influence : The Strategic Planning: SWOT Analysis assignment completed in Topic 4 helped you identify a strategic goal within your sphere of influence.
What is this inheritance worth : What is this inheritance worth to you today if you can earn 4.1 percent interest, compounded annually?
Print the given daily bar charts : BCOM 220, PROJECT PLANNING & CONTROL Exercise. Print the following Daily Bar Charts, list the activities in ES/EF sequence
What is the amount of producer surplus : The good can be produced at a constant cost of $10 for the first 20 units. After the first 20 units, the marginal cost equation is MC = 12Q.
Create a developmental plan outlining how you intend : Your supervisor at the agency where you work has become increasingly insistent that you work many hours over and above your required working hours.
What changes have occurred in the demographics of workforce : What changes have occurred in the demographics of the workforce with regard to gender, race or age with regard to your intended occupation?
Control information security : Give examples of security measures that might be used to control information security, personnel security, and health hazard security issues

Reviews

len1968357

5/3/2018 3:46:26 AM

Robert Dickison: Project Planning and Control. Details: Complete assignment 15 using the pdf. This exercise is designed to assess your base knowledge of report generation, as well as your proficiency with Microsoft Project. Please open your complied 51 5 Lab project in Microsoft Project . Submit all (8) PDF reports via this assignment link by the due date. Note: After creating PDFs of the reports check to see if they make sense to you, Look for overlaps on equipment; if there is sufficient float so that the available equipment can be worked within the float that is ok. You can do this project under about 90 days. To ensure a high grade, make certain you carefully read the reports.

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd