Assignment: Project Schedule Changes
You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation.
Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
Write a paper on period from world war ii through the 1970s
: Write a five to six page paper on the period from World War II through the 1970s.Your paper should cover the following: Identify at least two major historical turning points in the period under discussion.
|
What kind of liability is being reported
: In 2009, two small retail customers filed separate suits against the company alleging misrepresentation, breach of contract, conspiracy to violate federal laws, and state antitrust violations arising out of their purchase of retail grocery stores thr..
|
Identify the stakeholders the company must satisfy
: Identify the stakeholders the company must satisfy. Why is this process more difficult for companies operating internationally
|
Portion of ethics training for new employees
: A new group of employees has just started at your company. Your boss has asked you to assist in a portion of the ethics training for the new employees.
|
Presentation for senior management outlining
: Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan
|
Accounting budget mean automatically raising the goals
: Does ratcheting in Accounting budget mean automatically raising the goals or prices without considering changes to the business or economy?
|
Discussion-international equity and bond markets
: Earlier, the CFO of GBATT had you look at capital and financial structures in general. Now, the CFO has asked you to look at the international debt and equity markets available for GBATT as a precursor to possibly changing the firm's capital struc..
|
Interest was received by the straight-line method
: On April 1, 2014, West Company purchased $450,000 of 6.00% bonds for $467,750 plus accrued interest as an available for sale security. Interest is paid on July 1 and January 1 and the bonds mature on July 1, 2019. The bonds are sold on November 1, 20..
|
How organized crime gained a foothold in the united states
: How organized crime gained a foothold in the United States. How organized crime groups sought to influence government. The organization of organized crime groups in the post-Prohibition era.
|