You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.
You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.
In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.
Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.
You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.
You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.
Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.
What windows cli command will display
: What Windows CLI command will display all current resources that your computer is making available to other network users
|
Toxins in the body
: Activity - Toxins in the Body: List some of the toxins that persist in the human body, and the potential sources of those toxins in your environment. What are the substances that your body comes into contact with during a normal day? Make up a dialog..
|
The expansion of blue streak
: Arthur Benton started the Blue Streak Delivery Company five years ago. Blue Streak initially provided commercial delivery services for all packages within the city of Unionville (population 1 million).
|
Environmental proposal paper
: Environmental Proposal Paper
|
Presentation for senior management
: Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking app..
|
Write a research paper about globalization and immigration
: Write a research paper about globalization and Immigration, 1300 words due tomorow, and I have the outline. Who could help me?
|
Discuss the various gender inequalities in education
: Discuss the various gender inequalities in education
|
Company analysis report
: Assume that you have recently been hired as the director of continuous improvement of a company. You are an outside hire with limited history of the firm and personal capital at the firm, and you are responsible for lean production, total quality ..
|
Decide on strategic management plans
: In this assignment, you will decide on strategic management plans, a company's strategic competitiveness, and the best model for above-average returns.
|