You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000 (installation only). It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

a. At the end of week 1:

i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

b. At the end of week 3:

i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

c. At the end of the project:

i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

Reference no: EM1337380

Questions Cloud

Relationship between quality and competitiveness : Discuss the relationship between quality and competitiveness.
Rising jet fuel cost recently led most major us : Rising jet fuel cost recently led most major U.S. airlines to raise fares by approximately 15 percent. Explain how this substantial increase in airfares would affect the following:
Define multimedia sites that include audio and video : In the early 1990s, the Internet offered primarily text-based sites. Now Internet is rich in multimedia sites that include audio and video. What are some of the changes that needed to happen to the Internet in order to support this new functionalit..
Current it is illegal for parents who want to adopt a child : As we all know, at current it is illegal for parents who want to adopt a child to pay the birth mother for, or to offer to pay for, the babies they adopt.
Preparing a project to lay fiber optic cable : You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable.
What are the types of new ethernet equipment : An older network using 10baseT technology needs an upgrade. The network contains a total of 220 workstations and 10 servers and has a network diameter of 300 meters. What type of new Ethernet equipment would you suggest be purchase to modernize th..
Explain student query-marketing strategy : Explain Student query-marketing strategy and What are some examples in which strategy and the price appear to be inconsistent
He proposed an rise in ethanol produced from corn : He proposed an rise in ethanol produced from corn and stalks and leaves from corn and other grasses. What is the likely impact of these two events on food prices in the United States.
Preparing plans among group members : Some changes to your program. Discuss and begin to prepare plans among your group members how you will go about making modifications you should make to keep your sub-project on track.

Reviews

Write a Review

Project Management Questions & Answers

  Manufacturing quality dimensions to improve revenue

Which of the 4 manufacturing quality dimensions are most likely to improve revenue?

  Developing a list of key success indicators

Develop a list of "Key Success Indicators" that could and should have been measured on completion. Rank them in order of priority for this project.

  Importance of project sponsorship and leadership

Describe the importance of project sponsorship and leadership when it comes to escalating decisions during a project.

  Talk about fragmentary identities

Social psychologists and even sociologists a lot of times talk about fragmentary identities that exist in people bicultural people.

  Decision making in accounting and financial reporting

Identified and analyzed 3 roles of ethics as it relates to judgment and decision making in accounting and financial reporting.

  Computing the total cost for loan

Compute the total cost for each loan and calculate based on paying off option A in 15 years.

  Solution when team is becoming distracted by situation

The rest of team is becoming distracted by the situation and your project is getting off schedule. What do you do?

  Different strategies for managing conflict

Different people have different strategies for managing conflict. What is your opinion on how this negotiation will end?

  Expected net present value for project

What was Salem's expected net present value for this project?

  Enhancing steps associated with reengineering

Select the PERT technique you consider LEAST valuable when altering or enhancing steps associated with reengineering. Explain your choice. Describe and analyze how the two techniques you chose influence the Critical Path Method.

  Qualitative and quantitative risk analysis

What are the differences between qualitative and quantitative risk analysis? Explain.

  Explaining importance ethical and legal responsibilities

Explain the importance ethical and legal responsibilities in the research project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd