ABC Bhd uses a job order costing system in its production process. Production overhead is applied based on direct labor hours incurred. The following information concerns a customer order for the job number 1345H:

Direct materials used:

Requisition Number 1333 RM880

Requisition Number 1334 RM906

Requisition Number 1335 RM248

Direct labor:

Machining Department 8 hours at RM9 per hour

Assembly Department 5 hours at RM10 per hour

Inspection Department 7 hours at RM12 per hour

In addition, production overhead cost is applied to the job at the rate of RM11 per direct labor hour. The selling and distribution overhead is RM180. Profit markup is estimated at 25% of the total cost.

Problem 1: Prepare total cost for the job number 1345H.

Reference no: EM132762700

Questions Cloud

Identify significant vulnerable population : Identify a significant vulnerable population in your local area.
Find what is the yield to maturity of a fourteen-year bond : Find What is the yield to maturity of a 14-year bond that pays a coupon rate of 10.92 percent per year, has a $1,000 par value, and is currently priced at $707?
Distance between the third bright band : What is the distance between the third bright band and the fifth dark band of the interference pattern formed on a screen 2.50 m from the grating?
Explain the most appropriate auditors opinion : Using the Framework for Audit Opinions studied in this unit, explain the most appropriate auditor's opinion for Laksa Imports for the year ended 30th June 2020.
Prepare total cost for the job number for abc bhd : In addition, production overhead cost is applied to the job at the rate of RM11 per direct labor hour. Prepare total cost for the job number 1345H.
Assignment recovery : Discuss the strengths of both the short- and long-term recovery plans implemented to protect the interest of all areas affected by the disaster.
List the journal entry that should be prepared : List the journal entry that should be prepared by Blue City for each of the following transactions. If no journal entry is necessary, list "No Entry Required".
Separate between noise and detector effects : How does iZIP and HV benefit from this? What are the corresponding dark matter limits of the two detectors?
Find the highest point reached by the coin : A coin is tossed upward at an initial velocity of 5m/s a. Find the highest point reached by the coin.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd