Question - In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 2022 2023
Cost incurred during the year: $2,580,000 $4,042,000 $2,175,800
Est. costs- complete for year-end: 6,020,000 1,978,000 $0
Billings during the year: 2,060,000 4,562,000 3,378,000
Cash collections during the year: 1,830,000 4,200,000 3,970,000
Westgate recognizes revenue over time according to percentage of completion.
Complete the information required below to prepare the partial Balance Sheet for 2021 and 2022 showing any items related to the contract.