Reference no: EM133627266
Gong-Auto wants to open a new repair shop in the region. They have already bought suitable land to locate the repair shop. They have identified the following activities as part of the project to set up the warehouse.
A. Obtain the necessary approvals from agencies to build the warehouse.
B. Identify a suitable contractor to build the repair shop.
C. While the identification of the contractor is ongoing, design the repair shop with inputs from employees and an engineer.
D. Construct the repair shop.
E. Order the fixtures, fitings and equipment for the repair shop so that they would arrive to coincide with the completion of construction (fixtures, fitings and equipment can only be ordered once the design is finalised)
F. Install the fixtures, fitings and equipment and commission the repair shop.
Provide your estimates for each of these activities (in weeks) and prepare the network diagram for the project (estimation of activity durations will not carry marks). Show the earliest start time, earliest finish time, latest start tme and latest finish time for activities within the diagram. Also, highlight the critical path for the project.
Explain the significance of information that can be obtained through a network diagram.
Describe his seven deadly diseases
: Write a small essay about W. Edwards Deming and Toyota quality system. Describe his "Seven Deadly Diseases" and briefly discuss them.
|
Abusive supervision critically examine leadership issue
: Abusive supervision Critically examine leadership issue examine the impact these issues, challenges, and trends may have for both the short and long-term
|
Hydraulic circuit for construction machine
: Imagine you're tasked with designing a hydraulic circuit for a construction machine, such as an excavator, bulldozer, or compactor.
|
Maintenance is appropriate for the engine of the car
: xplain which type of maintenance is appropriate for the engine of the car, for tires and for light bulbs with justifications.
|
Prepare the network diagram for the project
: Gong-Auto wants to open a new repair shop in the region. Explain the significance of information that can be obtained through a network diagram.
|
Sourcing-self-sourcing and outsourcing
: A company has three primary choices regarding how its system will be created (in-sourcing, self-sourcing, and outsourcing).
|
Continue outsourcing the cleaning of bottles
: Using the Creemore Springs Case in the CoursePack you will assume that management has decided to continue outsourcing the cleaning of bottles
|
How can carrying inventory protect against stockouts
: How can carrying inventory protect against stockouts, balance supply/demand, and protect against uncertainty?
|
Suggestion in relation to total quality management
: Discuss the merits of this suggestion in relation to Total Quality Management (TQM) and suggest an alternative method of addressing the same problem
|