Reference no: EM132626647
The Unda Construction Company Limited began to work on July 1 on a parking bay contract awarded by Donge county valued at sh.14,000,000. The retention is 15%. As at December 15, the certified work done (gross) amounted to sh.6,400,000.
The following information regarding the contract is available:
sh.
Materials delivered direct to contract 1,600,000
Materials issued from stores 300,000
Wages 3,000,000
Apportionment of overhead to Dec. 31 500,000
Plant sent to contract at valuation 27,000,000
Plant returned from contract on Nov. 30 at valuation 17,800,000
Plant remaining on contract at Dec. 31 at valuation 8,600,000
Accrued wages to Dec. 31 130,000
Materials return to stores 60,000
Work done not yet certified @ Dec. 31, at cost 480,000
Materials on site at Dec. 31 350,000
Problem 1: You are required to prepare the contract account and recommend the profit to be recognised at Dec. 31