Reference no: EM132693596
Question - On July 1, 2020, Splish Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Splish estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022.
At 12/31/20 At 12/31/21 At 12/31/22
Contract costs incurred to date $312,900 $1,148,400 $2,076,000
Estimated costs to complete the contract 1,177,100 831,600 -0-
Billings to Gumbel 300,000 1,090,000 1,850,000
Required -
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022.