Prepare report to advice employer on the possible problems

Assignment Help Other Subject
Reference no: EM13884770

Question:

Kmart is a medium scale local retailer of clothing in your country who is currently the Employer (Client) of an on-going construction of a medium scale retail store in a prominent location in the Capital of the country. Having finalised the design development stages of the project, the Employer was in a hurry to start work. Hence it was keen to issue a Letter of Intent to the successful Contractor to commence the work rather than entering into a Contract with the Contractor. However, later on the Employer decided to execute a Contract with the Contractor. Currently, the development is underway. The traditional procurement route is used to acquire the project.

The project uses the "JCT Standard Building Contract with Quantities 2011" for contract administration purposes. The project includes construction of two interconnected buildings which is estimated at £7 million in total. Liquidated damages are set at £ 40,000 per day. Half way through the construction process of the plinth beams of the buildings, the Contractor realises some structural deficiencies in the beam sizes. The Contractor informed the Contract Administrator of this unexpected situation in writing and copied in the Clerk of Work. Having consulted the Contract Administrator, the Clerk of Work issued a Direction to break some of the plinth beams and replace them with new ones. The Contractor instructed its employees to proceed according to the Direction to break the beams and replace them. It now wishes to make an application for loss and expenses incurred in breaking and replacing the beams and request a time extension for the standing time on site when the problem was discovered.

The Contractor, when pricing the Oak stair handrails in the contract, has made an error and included a rate which is far too low. When work is completed, due to variations issued by the Contract Administrator, the quantity of the Oak stair handrails substantially increased. The Contractor now wishes to make an application for loss and expenses incurred for the excess quantity. The Contractor also wishes to request a time extension for the additional work involved, but has not submitted a delay notice which the contract states must be sent as a condition precedent to an extension of time entitlement. So far the Contractor has made ten applications for interim payments, but the Employer has only approved and paid six of them on time. On the other four occasions, the Employer has failed to pay by the final date for the relevant interim payments as agreed in the Contract.

Requirements of task

You are required to prepare a report to address the following pre and post contract administration issues of the above development:

a) If you were the Contract Administrator, prepare a report to advice the Employer on the possible problems associated with issue of a Letter of Intent rather than establishing a contract.

b) Critically evaluate the validity of Clerk of Work's Direction to break the plinth beams and replace them with new ones and the Contractor's response to the Direction.

c) Detail the legitimate applications for payment of loss and expenses (claims) that the Contractor can make with respect to the given scenario, the main facts that can be included in the application and the contractual provisions available to substantiate the application according to the JCT SBC/Q 2011. You also have to detail and discuss the instances where contractor wishes to submit applications for payment of loss and expenses, but still not legitimate according to JCT SBC/Q 2011, with appropriate justification with respect to the given scenario; and what other alternative contractual means available to cover the cost incurred (if cost is recoverable) in those instances.

d) Detail the legitimate time extension requests that the Contractor can make with respect to the given scenario, the information required to support these requests and the contractual provisions available to substantiate the requests according to JCT SBC/Q 2011. You also have to detail and discuss the instances where the Contractor wishes to submit time extension requests, but not legitimate according to JCT SBC/Q 2011, with appropriate justification with respect to the given scenario.

e) Discuss the contractual provisions in relation to the late interim payments by the Employer. You should support the answers with the relevant clauses in the JCT Standard Building Contract With Quantities 2011 Edition.

Additional requirement:

The problem related to Architectural Engineering and it discusses about developing a construction contract report for a chain store that wants to build a store.

Total Word Count 1700

Reference no: EM13884770

Questions Cloud

What are the ethical issues faced while enacting quarantine? : What are the ethical issues faced while enacting quarantine?
Fractional yield concept : The feed (CAo= 1.0, CRo= 0, CSo= 0) enters two mixed reactors in series (?1= 2.5 min,?2= 10 min) knowing the composition in the first reactor (CA1= 0.4, CR1= 0.4, CS1= 0.2),find the composition leaving the second reactor (using fractional yield co..
What is the efficiency of this cycle : A monatomic ideal gas (1 mole) undergoes this cycle: starting from 1 atm, 0? C, it contracts adiabatically to P = 2 atm, then it expands isothermally, then it contracts isobarically. (a) Sketch the cycle, indicating P, V, and T, for all points. (b..
Prepare report to advice employer on the possible problems : Prepare a report to advice the Employer on the possible problems associated with issue of a Letter of Intent rather than establishing a contract.
Determination of the effects of changes in exchange rates : Determination of the effects of changes in exchange rates. Determination of policies governing sales of merchandise on credit. Determination of whether to use the periodic or the perpetual inventory system.
What are the main roles of the government in the us health : What are the main roles of the government in the US health services system?
Calculation of profit using completed contract method : Kiner, Inc. began work in 2012 on a contract for $12,600,000. Other data are as follows: This problem related to Basics Accounting and calculation of profit using completed contract method
Represent the velocity of the plane : A small plane flying at a speed of 180 miles per hour on a bearing of N50E. the wind is blowing from west to east at 40 miles per hour. Let v represent the velocity of the plane in still air and w represent the velocity of the wind.

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd