Reference no: EM132582216
On 1 October 20X0 Monna entered into a construction contract that was expected to take 27 months and therefore be completed on 31 December 20X2. Details of the contract are:
Agreed contract price RM12,500
Estimated total cost of contract (excluding plant) RM 5,500
Plant for use on the contract was purchased on 1 January 20X1 (three months into the contract as it was not required at the start) at a cost of $8 million. The plant has a four-year life and after two years, when the contract is complete, it will be transferred to another contract at its carrying amount. Annual depreciation is calculated using the straight-line method (assuming a nil residual value) and charged to the contract on a monthly basis at 1/12 of the annual charge.
The correctly reported profit or loss results for the contract for the year ended 31 March 20X1 were:
RM'000
Revenue recognized 3,500
Contract expenses recognized (2,660)
Profit recognized 840
Details of the progress of the contract at 31 March 20X2 are:
RM'000
Contract costs incurred to date (excluding depreciation) 4,800
Agreed value of work completed and billed to date 8,125
Total cash received to date (payments on account) 7,725
The percentage of completion is calculated as the agreed value of work completed as a percentage of the agreed contract price.
Required:
Question 1: Prepare extracts of the statement of comprehensive income for the year ended 31 March 20x2.
Question 2: Prepare extracts of the statement of financial position as at 31 March 20x2. (Show all necessary workings)