Reference no: EM132573688
Sunkanmi Ltd., commenced work on shopping complex for Ona Ara Local Government on 1 st January, 2019. The contract price is N8, 100,000. As at 31st December, 2019 the following cost have been incurred by contractor:
N'000
Machineries and equipment purchased 810
Labour cost as at 31 st December 1,620
Materials sent to site 2,025
Direct cost 324
Establishment expenses 675
Materials unused at 31 st December 203
Materials returned to store 68
Labour cost unpaid as at 31st December 67
Direct cost unpaid as at 3 1 st December 14
Value of machineries and equipment at 31 st December 540
Cost work not yet certified 405
Cash received so far 4,860
As at 31st December, 2019, the certificate of work approved amounted to N5,400,000. It is the policy of the Local Government to keep 10% of contract price as a retention fees.
Required:
Question 1: Prepare the contract account, contractee account and value of work-in-progress.