Reference no: EM132758690
Question 1: Calculate the equipment and labour prices per m3 to excavate 3000 m3 of trench using 0.75 m3 backhoe costing RO 14/day (day = 8 hrs), plus RO 90 for transportation and set up charges. Expected output is 60 m3 /day with an operator and 0.5 labour at wages of RO 24/day and RO 16/day respectively.
Write a specification for the above work.
Question 2: It is required to determine the unit price for plain concrete given the following information: Plain concrete (PC) quantity = 1080 m3. One cubic meter of Plain Concrete comprises of 250 kg cement; 0.8 m3 gravel and 0.4 m3 sand. The prices of these materials are RO500/ton; RO80/m3 and RO40/m3 for cement, gravel and sand respectively. Assume 10% wastage for all these materials. The details of the crew used are shown in the table below. Assume overheads and markup 20%
Table 2.1 - Detail of the Crew Item
Crew Item
|
Number
|
Production
|
Price rate
|
Pump
|
1
|
30 m3/hr
|
RO 55/day
|
Truck mixer
|
3
|
9 m3/hr/one
|
RO40/day/one
|
Vibrator
|
2
|
|
RO15/day/one
|
Labor
|
5
|
|
RO16/day/one
|
Foreman
|
1
|
|
RO 35/day/one
|
Question 3: You are a junior estimator working for a medium scale construction company in Oman. You have been assigned to formulate a specific rate for 400 m2 gloss paint for a project that the company is intending to tender. The specification is as follows:
1. Prepare and apply one coat of plaster primer,
2. One flat oil undercoat and
3. Two coats of gloss finish oil paint to plaster wall
Assume an Overhead and profit of 25%.
Assume the average area of coverage for every 5lts:
i. For Plaster primer is 55m2
ii. For Flat oil undercoat is 65m2
iii. For Gloss finish oil paint is 68m2
The cost of 5 litres of Primer is RO 8.50, The cost of 5 litres of Flat Oil Undercoat is RO 10.25 and the cost of 5 litres of Gloss Finish is RO 12.85
Assume residue waste on paint to be 10%
Labour specification:
1. Painter's time to cover 100m2 of primer 11 hrs
2. Painter's time to cover 100m2 of undercoat 09 hrs
3. Painter's time to cover 100m2 of Gloss paint 14 hrs
4. Rate of painter per hour is RO 4.35.
Assume 10% for sundries cost for paint brush, roller, sand paper etc
Question 4: Calculate the price of obtaining a gravel form a pit located 16 km from the work site, where unit price is RO15/m3, using a loader with a rate of 50 m3 /hr (bank measure) and 12 m3 trucks to transport the gravel. The loader and trucks are priced at rates of RO 75/day and RO 45/day respectively. The labour crew consists of one equipment operator at RO 3.85/hr, two labours at RO1.85/hr and truck driver at RO 2.75/hr. The dump truck travel at an average speed of 20 km/hr. the gravel has swell factor of 12% and 5 minute required to off-load the truck.