1. The following are data for two IT projects for a new database system. Prepare a spreadsheet for two projects, using the following data. Amounts are in thousands of dollars. Calculate the NPV for each.  (Please assume a Discount Rate of 10%)

 

Year 1

Year 2

Year 3

Year 4

Year 5

Total

Project 1

 

 

 

 

 

 

Benefits

$0

$2,000

$3,000

$4,000

$5,000

tbd

Costs

$5,000

$1,000

$1,000

$1,000

$1,000

tbd

Cashflow

($5,000)

$1,000

$2,000

$3,000

$4,000

$5,000

Project 2

 

 

 

 

 

 

Benefits

$2,000

$3,000

$5,000

$3,000

$1,000

tbd

Costs

$2,000

$2,000

$2,000

$2,000

$1,000

tbd

Cashflow

$0

$1,000

$3,000

$1,000

$0

$5,000

2.  Prepare a precedence diagram for the following tasks. All tasks have a finish-to-start relationship.

Task

Duration

Preceded By

Followed By

A

1

None

B, C, D

B

2

A

E

C

3

A

E, F

D

4

A

G

E

5

B, C

F

F

6

C

H

G

7

D

H

H

8

E, F, G

None

3.  Prepare a Gantt chart for the tasks shown for question 2. (This can be hand drawn if you have no software to make it, and then you can take a picture of your drawing and included it in this document as an image).

4.  Determine the critical path for the tasks shown for question 2.

5.  Your company is planning to launch a new IT project starting July 1 that will last one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior systems analysts for the whole year, four programmers for the months of February-May, and one full-time technical writer for the last three months. Create a stacked column chart using Excel that shows resources by month. Provide appropriate titles, axes labels, and legends. 

6.  Take the MBTI. There are several websites you can use: www.humanmetrics.com, www.personalitytype.com, and www.kiersey.com. Write a one-page summary discussing your MBTI type and its opposite MBTI type. For example, if you are an INTJ, then its opposite is ESFP. What challenges would you see working with this person on a project? What you think about the MBTI as a team-building tool?

 

7.  Your IT consulting company is trying to decide which of four projects to bid. Information on each is in the table below. Assume that all up-front investments are not recovered, so they are shown as negative profits. Draw a diagram and calculate the expected monetary value (EMV) for each project. Write a paragraph explaining which project(s) you would choose to bid.

Project

Chance of Outcome

Estimated Profit

Project 1

50%?50%

$120,000?-$50,000

Project 2

30%?40%?30%

$100,000?$50,000?-$60,000

Project 3

70%?30%

$20,000?-$5,000

Project 4

30%?30%?20%?20%

$40,000?$30,000?$20,000?-$50,000

8.  Your company has a technical support line for customers to call. Create a Pareto diagram based on the information in the following table. Create a spreadsheet using these data. List the most frequent complaint first. Then add a column labeled "% of Total" and another labeled "Cumulative %". Then enter formulas to calculate these items. Then use the Excel Chart Wizard to create a Pareto diagram based on the data. Use the Line - Column on 2 Axis custom type chart so that your resulting chart looks similar to the one in Figure 8-1.

 

Customer Complaints

Frequency/Week

Customer is on hold too long

90

Customer gets transferred to wrong number

20

Customer gets cut off

50

Service rep cannot answer customer's question

120

Service rep does not follow through as promised

40

Service rep is rude

10

9.  Use the following WBS and duration information for a project to build a new website. Prepare a Gantt chart and a precedence diagram. Determine the critical path.

1.

Initiating

1 week

 

2.

Planning

4 weeks, starting after Initiating ends

 

3.

Executing

 

 

 

3.1 Conduct User Interview

6 weeks, starts after Initiating ends

 

 

3.2 Conduct User Survey

4 weeks, starts midway through User Interviews

 

 

3.3 Site Content

 

 

 

 

3.3.1 Develop Templates

12 weeks, starts after User Interviews and User Survey end

 

 

3.3.2 Write Articles

8 weeks, stats anytime after Site Content begins

 

 

3.3.3 Prepare FAQ

2 weeks, starts after User Interviews and User Survey ends

 

3.4 Design Site

8 weeks, starts after User Interviews and User Survey end

 

 

3.5 Build Site

16 weeks, starts after Design Site ends

 

 

3.6 Perform Integration Testing

2 weeks, starts after Build Site ends

 

 

3.7 Conduct Acceptance Tests

2 weeks, starts after Integration Testing ends

 

4.

Controlling

runs for entire duration of project

 

5.

Closing

1 weeks, follows Acceptance Testing

 

10. Using the following information for a one-year software development project, answer the following four questions.

  • PV = $23,000
  • EV = $20,000
  • AC = $25,000
  • BAC = $120,000

a. What are the cost variance, schedule variance, cost performance index, and schedule performance index for the project?

b. How is the project doing? Is it ahead of schedule or behind? Is it under budget or over?

c. Use CPI to calculate the estimate at completion (EAC)? Is the project performing better or worse than planned?

d. Use SPI as your guide, how long will it take to finish the project?

Reference no: EM131561019

Questions Cloud

Explore current issues in ethics : Explore current issues in ethics, and propose a foundation for your organization's ethical practices, such as going green or fair labor standards
Value of establishing the habit of saving for retirement : Most if not all of us are taught the value of establishing the habit of saving for retirement.
Calculate the effective annual rate of interest on this loan : Calculate the effective annual rate of interest on this loan.
What is the dollar amount of interest that an investor : What is the dollar amount of interest that an investor will receive from this paper? What is the effective annual rate of interest on this commercial paper?
Prepare a spreadsheet for two projects : The following are data for two IT projects for a new database system. Prepare a spreadsheet for two projects, using the following data.
Define three common terms used in toxicology : Define three common terms used in toxicology. In addition, evaluate how media influence (including social media) may impact present situations in this field.
Direct material-direct labor and factory overhead : The job cost sheet is used to accumulate the three product costs: direct material, direct labor, and factory overhead.
Develop corporate strategy to formulate environmental policy : You have been tasked with developing a corporate strategy to formulate environmental policy that will be presented to local and state legislators.
Do you feel that scientists should be cut out of the policy : Do you feel that scientists should be cut out of the policy making process, particularly on environmental issues, when their research is proven.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd