Prepare a sample of a good weekly progress report

Assignment Help Project Management
Reference no: EM132974872

Part 5 A: Project Resource Management
Several people working on the Recreation and Wellness Intranet Project are confused about their responsibilities for the testing portion of the project. Recall that the team members include you, a programmer/analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer/analyst. Tony Prince is the project manager, and he has been working closely with managers in other departments to make sure everyone knows what's going on with the project.

1. Prepare a responsibility assignment matrix based on the following information: The main tasks for testing include writing a test plan, unit testing, integration testing for each of the main system modules (registration, tracking, and incentives), system testing, and user acceptance testing. In addition to the project team members, a team of user representatives is available to help with testing, and Tony has also hired an outside consulting firm to help as needed. Prepare a RACI chart to help clarify roles and responsibilities for these testing tasks. Document key assumptions you make in preparing the chart.

2. The employees of the outside consulting firm and the user representatives have asked you to create a resource histogram to show how many people you think the project will need for testing, and to show when testing will occur. Assume that the consulting firm has junior and senior testers and that the user group has workers and managers. You estimate that you'll need the involvement of both groups in testing over a period of six weeks. Assume that you'll need one senior tester for all six weeks, two junior testers for the last four weeks, two user-group workers for the first week, four user-group workers for the last three weeks, and two user-group managers for the last two weeks. Create a resource histogram using the resource histogram template based on this information.

3. One of the issues Tony identified is the ability to work effectively with the user group during testing. According to MBTI classifications, Tony knows that several of his project team members are very introverted and strong thinking types, while several members of the user group are very extroverted and strong feeling types. Write a one-page paper that describes options for resolving this issue, focusing on using a confrontation/problem-solving approach.

Part 5 B: Project Communications Management
Several issues have arisen on the Recreation and Wellness Intranet Project. The person from the HR department who was supporting the project left the company, and now the team needs more support from that group. A member of the user group that supports the project is extremely vocal and hard to work with, and other users can hardly get a word in at meetings. The project manager, Tony, is getting weekly status reports from all of his team members, but many of them do not address obvious challenges that people are facing. The team is having difficulty deciding how to communicate various project reports and documents and where to store all of the information being generated. Recall that the team members include you, a programmer/analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer/analyst.

1. Summarize three different communications media that could be used for getting more support from the HR department and which you think would be most effective.

2. Prepare a partial communications management plan using communication management plan template to address some of the challenges mentioned in the previous paragraph.

3. Prepare a sample of a good weekly progress report that could be used for this project. Include a list of tips to help team members provide information on these reports. Also include the burndown chart using the burndown chart template.

4. Write a one-page paper describing two suggested approaches for communicating with the hard-to- work-with user.

Reference no: EM132974872

Questions Cloud

What is the current price : A bond pays semi-annual coupons with a coupon rate of 12%. Yield to maturity is 13.4% and the bond has five years until it matures. What is the current price
Can corporations be imprisoned : What penalty or penalties did BP incur after pleading guilty to eleven counts of manslaughter?
What is a stewardship theory : What is a 'Stewardship Theory'? With reference to literature please explain how agents would act to demonstrate good stewardship
Identify a learning opportunity in organization : Identify a learning opportunity in your organization or an organization with which you are familiar. Describe the ways in which motivation is a factor
Prepare a sample of a good weekly progress report : Summarize three different communications media that could be used for getting more support from the HR department and which you think would be most effective
What is the pressure of the carbon dioxide in atmospheres : The pressure of the collected gas (water vapor + carbon dioxide) has a pressure of 0.789 atm, what is the pressure of the carbon dioxide in atmospheres (atm)?
What is Taylor tax : For 2020, she has the following income: $4,000 wages from a summer job, $1,800 interest from a money market account, What is Taylor tax
Credit default swaps and collateralized debt obligations : Fixed income derivatives such as credit default swaps and collateralized debt obligations are viewed with suspicion in the wake of the subprime crisis. Is this
Develop a list of quality standards : Develop a list of quality standards or requirements related to meeting the stakeholder expectations described in the Running Case.

Reviews

Write a Review

Project Management Questions & Answers

  Compute the total slack for each activity

Compute the Total Slack for each activity. Determine which activities are on the critical path. How long will it take to complete the project?

  How much slack is currently available in non-critical path

What is the duration of the project? How much slack is currently available in the non-critical path? How long are the project and feeder buffers?

  Provide a consultancy report about the project

Chief Executive Officer of the company of your chosen scenario to provide a 1000-word consultancy report about the project that is going to be delivered.

  Describe three leadership traits identified by dubrin

Describe three (3) leadership traits identified by DuBrin. How did Commander D. Michael Abrashoff use these traits to effectively command the USS Benfold?

  You are required to submit a written assignment relating to

you are required to submit a written assignment relating to new product development.in this assignment you will show a

  Suitability and reliability in qualitysuitability and

suitability and reliability in qualitysuitability and reliability are two examples of quality in terms of buying

  Discuss the validity of each statement

Discuss the validity of each statement.-  If the statement is always true, explain why. If not, give a counterexample.

  Appropriate project-oriented development process

How does a project manager choose the appropriate project-oriented development process is an important decision.

  What is unrelated business income

How do federal income taxes treat dividends received by corporations compared to dividends received by individuals?

  What additional capabilities does mrp possess

MRP is more than an inventory system; what additional capabilities does MRP possess? What are the options for the production planner who has: scheduled more than capacity in a work center next week?

  Using the cut-and-try method for aggregate operations

Using the cut-and-try method for aggregate operations planning we can determine the production requirement in units of product. If the beginning inventory is 100 units

  Organizational culture and project managementplease answer

organizational culture and project managementplease answer the questions. i have several books about the info but i am

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd