Post-Leave Report:
• Engineering Dept.:
o Riyadh:
Phase 1,
• 18 Rooms completed with physical installation of power and network outlets.
• Back-end power connected,
• Back-end network to be connected, issue with Network Team
o Jeddah:
HITA switches 1 (out of 2) unit are installed in OR areas,
• Node activation currently under process.
• HITA additional switches SPR under approval.
Phase 2
• 5 out of 7 rooms completed
• Simulation Room:
o R/J
Escalated to CTO because no response from engineering department. The Engineering is debating of having external contractors for the design in the CTO meeting.
ADS team will be using the room in Jeddah without interior design in order to schedule phase 1 trainings.
• Finance Requirements:
o Master list from SCMSolutions received
With consumption per cost center
but prices need to added
• Gulf Medical:
o Venus testing completed from HITA-side, need to test with prices
o Kanban sample to be delivered for Engr. review and installation in Sim Room.
o Training for XT Cabinet can be conducted for Phase 1 Users.
• Alshaya:
o Bins
Initial approval received from Medical Store regarding Bins /Dividers.
Heart Center approved the bins for there are also
Selected 4 sizes, requested revised quote from manufacturer
o Initial order of shelves have been delivered
o Finalize procurement of shelf Labels.
• Oracle BRD
o ADS Team and Sarah Alkahtani to map the oracle touchpoints in specialty areas R/J.
• Phase 1-R Delivery
o Internal coordination on-going