You are preparing a project to lay fiber optic cable...

You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000. It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

a. At the end of week 1:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

b. At the end of week 3:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

c. At the end of the project:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

Reference no: EM1343235

Questions Cloud

Project management of applications : Project Management of Applications - Show the role of the project manager in the in-house development of a customized application.
Show the project cash flow analysis : Your company plans to produce a product for two more years and then to shut down production and you are considering replacing an old machine used in production with a new machine.
Monitoring and controlling project cost : Earned Value Analysis - Monitoring and Controlling Project Cost - What are some key components to monitor the health of the project, as it relates to earned value?
Question about milton manufacturing overhead activity : Evaluate the company's bid if the bid is based upon full manufacturing cost plus 30 percent and evaluate the amount of overhead that would be applied to the proposed project if activity-based costing is used.
Prepare a project to lay fiber optic cable : Prepare a project to lay fiber optic cable - What is your SPI and what is your CPI
Modify the integrated project plan : Modify the integrated project plan as a result of a team meeting to incorporate the changes to the plan as provided by the CBDF and the trickiest part of this assignment is to evaluate how you will do this.
Entertainment - due to electrical code changes : All the equipment that bands bring to the stage will need to be checked by fire marshals
Show the integrated project plan : Post the liquor license; validating IDs, validating the per-person limit, etc.
Risk management - identifying risks : Risk Management: Identifying Risks - Risk management is a matter of identifying the situations that could cause your project to fail.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd