Prepare a production budget for each of months july-october

Assignment Help Managerial Accounting
Reference no: EM132637494

Integration of the Sales, Production, and Direct Materials Budgets Milo Company manufactures beach umbrellas. The company is preparing detailed budgets for the

Third quarter and has assembled the following information to assist in the budget preparation:

A. the Marketing Department has estimated sales as follows for the remainder of the year (in units):

July . . . . . . . . . . . . . . . . . . . 30,000 October . . . . . . . . . . . . . . . . 20,000

August . . . . . . . . . . . . . . . . . 70,000 November . . . . . . . . . . . . . . 10,000

September . . . . . . . . . . . . . . 50,000 December . . . . . . . . . . . . . . 10,000

The selling price of the beach umbrellas is $12 per unit.

B. All sales are on account. Based on past experience, sales are collected in the following pattern:

30% in the month of sale

65% in the month following sale

5% uncollectible

Sales for June totaled $300,000.

C. The company maintains finished goods inventories equal to 15% of the following months Sales. This requirement will be met at the end of June.

D. Each beach umbrella requires 4 feet of Gilden, a material that is sometimes hard to acquire. Therefore, the company requires that the ending inventory of Gilden be equal to 50% of the Following month's production needs.

The inventory of Gilden on hand at the beginning and End of the quarter will be:

June 30 . . . . . ...... . . 72,000 feet

September 30 . . . . . . . . . ? Feet

E. Gilden costs $0.80 per foot. One-half of a month's purchases of Gilden is paid for in the Month of purchase; the remainder is paid for in the following month. The accounts payable on July 1 for purchases of Gilden during June will be $76,000.

Required:

Question 1. Prepare a sales budget, by month and in total, for the third quarter. (Show your budget in both units and dollars.) Also prepare a schedule of expected cash collections, by month and in total, for the third quarter.

Question 2. Prepare a production budget for each of the months July-October.

Question 3. Prepare a direct materials budget for Gilden, by month and in total, for the third quarter. Also prepare a schedule of expected cash disbursements for Gilden, by month and in total, for the Third quarter.

Reference no: EM132637494

Questions Cloud

Find out project development timeline : What experiences have you had with business training and support?
Find the cost of the finishing department ending work : Determine the cost of the finishing department's ending work in process inventory. At the end of the accounting period, 400 sets of skis were estimated.
How quickly you can get new environments set up : Which tenet of IBM Cloud Private makes it easier to build applications more quickly, leveraging existing content from a catalog
How power tools in excel could be used at work or home : Discuss (2) reasons an advanced user would choose to use Power Tools in Excel.
Prepare a production budget for each of months july-october : Prepare a production budget for each of the months July-October. Integration of the Sales, Production, and Direct Materials Budgets Milo Company manufactures
What is total amount that will classified as Current Assets : If the items are not Cash and Cash Equivalent, what is the total amount that will be classified as Current Assets
Display the total once after the loop terminates : Keep a running total of the values entered by your user. Display the total once after the loop terminates.
Mapping between user-level threads and kernel-threads : Consider an environment in which there is a one-to-one mapping between user-level threads and kernel-threads that allows
Example of sorting an array of strings using c language : Could you please give me a basic example of sorting an array of strings using C language?

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd