Prepare a partial construction budget

Assignment Help Civil Engineering
Reference no: EM133145518

Question: For this assignment, your task is to prepare a partial construction budget estimate for a small office building project using the budget spreadsheet template attached to this assignment. You may suggest an alternative building of your choice if you choose to do so. This can be a project you are involved with or very familiar with, but please keep the scope manageable and preferably comparable to the one suggested.

Submit the completed Excel worksheet to the assignment on Brightspace course website. This cost will be used as the benchmark for your analysis in following assignments.

Building size

100 ft x 100 ft with 25 ft by 25 ft structural bays; 15 ft floor-floor height, two levels

Building floors

6" slab on grade with troweled finish; 24" x 24" x 12" spread footings for columns; above-grade occupied floors are poured in place concrete on 18 gauge 3" deep corrugated steel deck; roof deck is lightweight concrete on the same steel deck

Building envelope

Brick walls; loose-laid and ballasted 60 mil EPDM roof membrane

Elevators and stairs

Two 2500 lb. capacity hydraulic elevators, two sets of 3'-6" wide straight stairs with 18 risers each and wall mounted handrails both sides.

Attachment:- CostProgram example.rar

Reference no: EM133145518

Questions Cloud

Aleut people viewed by the american government : How were Unangax/Aleut people viewed by the American government? What is one of the impacts of the Unangax/Aleut internment/relocation?
What was the account balance of the account on december : If the Warranty Payable account began 2019 with a credit balance of $50,000, what was the account balance of the account on December 31, 2019
How impacts the international flow of funds : Pick one news story about China from this year (2022). explain how this impacts the international flow of funds. Please reference your example.
How may many entries do the company make : For Sales Returns, if the inventory is damage and not saleable, how may many entries do the company make? Why
Prepare a partial construction budget : Prepare a partial construction budget estimate for a small office building project using the budget spreadsheet template attached to this assignment
How would you put the information into bank reconciliation : Question - How would you put the information below into a bank reconciliation for Jordy Co. for August 31, 2020
Six-step process for the development of the ea : As a part of using the six-step process for the development of the EA, the architects need to focus on the data types required. Which step of the six-step helps
Calculate the annual provincial income taxes : A normal workweek for any employee is 7.5 hours per day from Monday through Friday. Calculate the annual provincial income taxes
Assignment on marketing strategies : 1. Using paragraphs, discuss market analysis techniques you should use as part of a marketing and communication strategy, for the following: . Creating profiles

Reviews

Write a Review

Civil Engineering Questions & Answers

  Find the difference in depth of the liquid from the inside

Liquid flows with a free surface around a bend. The liquid is inviscid and incompressible, and the flow is steady and irrotational. The velocity varied with the radius across the flow as V = 1/r m/s where r is in meters.

  What do you think is the best ratio of b/y to use in your

A canal of rectangular cross-section and an n=0.030 is to be laid on a slope of 0.002 and is to carry a discharge of 30 m3/s. Calculate the cross-sectional area required for the channel to carry this flow based on the norma

  Determine the height from the ground and the time at which

Ball A is thrown vertically upward from the top of a30-m-high-building with initial velocity of 5m/s. At the same instant another ball B is thrown upward from the ground with aninitial velocity of 20m/s. Determine the height from the ground andthe ti..

  Compute loading on the floor in newtons per square meter

A total of 6800 kg of a bulk fertilizer is stored in a flat-bottomed bin having side dimensions 5.0 m x 3.5 m. compute the loading on the floor in newtons per square meter, or pascals.

  Determine how many feet of fence will be needed

A local contractor has just bought warehouse and decided to fence in an area of 1152 square feet behind the warehouse.He plans to use the wall of the building as one of the four sides that will enclose the rectangular area.

  How far upstream is depth within 100mm of uniform depth

A dam located in a channel of rectangular cross-section which carries water flowing at a rate of 8.75m3/s. The depth of water upstream of the dam is 2.5m. the channel is 5m wide,

  What is the relationship between precipitation rate and then

For this landfill, what is the relationship between precipitation rate and then resulting rise in water level within the drainage layer? Display your analysis graphically, corresponding to a minimum of the five rainfall intensities of magnitude 1-5".

  Determine substrate concentration and biomass concentration

How would you determine the substrate concentration and biomass concentration at 0.5 days - Use spreadsheet to solve for the concentrations with a delta t = 0.01 days.

  How does a database interact with data and information

Information is processed data; that is, it is organized, meaningful, and useful. In addition to documents, information can be in the form of audio, images, and video.

  Can it be concluded that fewer than half of the incinerators

Incinerators can be a source of hazardous emissions into the atmosphere. Stack gas samples were collected from a sample of 50 incinerators in Chicago. Of the 50 samples

  Find the emissivity of the metal part

Using the results of Prob. 8.47, determine the true metal temperature when the pyrometer indicates 450?C and the uncertainty in this temperature.

  Compute the permability based on the conditions and results

A constant head permability test is performed on a soil that is 2 cm X 2 cm square and 2.5 cm long. The head difference applied during the test is 18 cm, and 5 cm^3 is collected over a time of 100 sec.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd