A ski repair shop at a resort in Colorado sells replacement poles each season. The shop needs to develop a forecast of next season's sales so that they can place an order for poles with their supplier well in advance of the beginning of the season. Sales data for the past five years are shown below. Compare the forecasts given by the following models.

Year:               1       2     3     4      5
Sales (units): 350   375  355  375  390

Develop forecasts using:

a. A 5 year moving average.
b. A weighted moving average model with weights of 0.2, 0.2, 0.1, 0.3, and 0.2 for years 1 through 5 respectively.
c. An exponential smoothing model with year 1 forecast of 380 and α= 0.3.

Assignment 2

Togo makes riding lawn mowers and tractors. The company's expected quarterly demand is given below in the chart. The company will have 300 mowers in inventory at the beginning of the month and desires to maintain at least that number at the end of each month. Below is other critical data:

Production cost per unit = $225
Inventory Carrying cost per quarter per unit = $50 (based on ending inventory)
Hiring Cost per worker = $450
Firing cost per worker = $800
Beginning # of workers = 50

Each worker can produce 110 units per quarter

Complete the tables and calculate the cost of the two plans

LEVEL Plan

Quarter

Demand

Regular Production

Ending Inventory

Workers Required

Hire

Fire

1

5000

         

2

9000

         

3

7000

         

4

9000

         

Total

30,000

3

       

CHASE PLAN

Quarter

Demand

Regular Production

Ending Inventory

Workers Required

Hire

Fire

1

5000

         

2

9000

         

3

7000

         

4

9000

         

Total

30,000

         

Assignment 3

Calculate the processing load, available capacity, and develop the load profile for the stereo speaker subassembly. Two employees work the assembly process for 40 hours each.

a. Complete the load chart
b. Prepare a load profile chart from this data.
c. As the planner, what concerns do you have and what changes would you make if any?

 

Part Name:  Stereo speaker

Processing Time =  20 minutes

Week 1

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week

Planned Order Releases

220

190

210

270

210

190

240

200

Processing Load (hours)

 

 

 

 

 

 

 

 

Available Capacity (hours)

 

 

 

 

 

 

 

 

Reference no: EM131857766

Questions Cloud

Construct a project charter to revamp the compensation : You have recently been appointed head of human resources and are now in charge of managing a small team. Your next project is to revamp the compensation.
Dollar exchange rate over the past six months : What has been happening to the euro/dollar exchange rate over the past six months? Why? (Give an analysis)
Benefits to apple of outsourcing the assembly : What are the benefits to Apple of outsourcing the assembly of the iPhone to foreign countries, and particularly to China?
Managerial economics and globalization : Assume a startup health care company faces the following weekly demand and short-run cost functions:
Prepare a load profile chart from the given data : Prepare a load profile chart from this data. As the planner, what concerns do you have and what changes would you make if any?
How can a firm maximise profits : 1. Which of the following is a macroeconomic question? A How can a firm maximise profits, given the state of the economy?
Compare price ceiling and price floor using demand : Compare price ceiling and price floor using demand and supply curves discussed in class.
Trends you are experiencing in your various organizations : What are some of the trends you are experiencing in your various organizations and/or fields related to compensation and benefits?
When there is no change in demand but decrease in supply : When there is no change in demand but decrease in supply, how about changes in equilibrium price and quantity, increase or decrease?

Reviews

Write a Review

Supply Chain Management Questions & Answers

  Supply chain network design for cwc

This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?

  Criteria when making new location decisions

Identify a number of the typical criteria used when making new location decisions

  Draw the project network

Determine the mean critical path for Brent's job search process. What is the variance of the project duration?

  Compare and contrast economic - market, and relevancy

Please compare and contrast economic, market, and relevancy value.

  Brushing up on inventory control

Health system in Pennsylvania

  Supply chain strategy

Supply chain strategy

  What is the economic order quantity for fans in units

Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.

  What factors reduce the capacity of the organization

What factors reduce the capacity of the organization to get its objectives?

  What is the total annual cost

What is the total annual cost

  Supply chain management questions

Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.

  Explain the supply chain management concept

Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies

  How warehouses can add value in the supply chain

How warehouses can add value in the supply chain

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd