Reference no: EM133063423
Question - A firm of building contractors undertook a contract for INR 350000. The Following particulars are furnished for the year ended 31st December, 2020: Materials: Wages for Labour 40,000 Direct Purchased 30,000
General Plant in use:
Issued from Stores 10,000
Direct Expenses 2,500
WDV 90000 dep thereon 10000
Subcontract Charges 6,000 Share of General Overhead 2000 Materials as on 31.12.2020 2,000
Material Lost by Fire 500 o/s Wages on 31.12.2020 6,000
Direct Expenses Accrued on 31.12.2020 1000
Cash Received (90% of work certified) 1,62,000
Cost of uncertified work 5,000
Prepare a contract account.