Prepare a construction method statement

Assignment Help Other Engineering
Reference no: EM131489431 , Length: word count:4000

Introduction

Project Iron Boomerang (PIB) is a large Australian megaproject that has been proposed by a Queensland company, East West Parks Pty Limited. (See reference below)

A key component of the project is the construction of a 3,300km single line railway linking the Pilbara in WA and Queensland. The railway line will require the construction of a series of long length viaducts to cross the numerous floodplains that will be bisected by the new railway along the route. The viaducts will be constructed using precast concrete segmental girder sections, 24 and 32m in length that are ‘cast in situ' in on site ‘casting plants', transported and supported on 6m or 10m height bridge piers using a ‘bridge girder erection' vehicle (see reference below). The viaduct piers will also be constructed using precast concrete sections that are located on 30m depth bored pile footings.

Four viaduct options are being considered (refer Table below) and a key consideration is the length of time taken to build the viaduct because of the impact of the wet season (November to April) on construction. It is assumed that all necessary earthworks for the railway will have been completed prior to any work commencing on the viaducts.

TABLE - VIADUCT OPTIONS

Viaduct Type No.:

Viaduct Length (m)

Span of Girder between piers (m)

Height of pier from - ground level to girder underside (m)

The last digit of your enrolment number

1

1920

32

6

1,2

2

1920

24

7

3,4,5

3

1920

32

8

6,7

4

1920

24

9

8,9,0


Note: Which Option do I do? Use the last digit of your Swinburne Enrolment Number and refer to the last column of the Table above.

Questions

1. Define the following:

- Linear Project
- Time Chainage Diagram

2. Prepare a construction schedule (having a start date of 1 January 2020) in Time-Chainage Diagram (TCD) format using AutoCAD, XL or other graphical software showing all activities to be undertaken for the construction of¬your viaductoptionwhich shall include site establishment, building a casting yard,casting of the viaduct segments and construction plant set up. Include all assumptions and calculations for estimating construction activity durations. Detail on your TCD the finish date for the works and the duration. Assume that work on the viaduct construction site will be undertaken on a 6-day week basis.

3. Prepare a Construction Method Statement (see format in reference below)outlining the steps involved in the construction of all aspects of your viaduct option. Include a detailed list of construction plant and equipment that would be utilised on the project. Provide details of the hazards and risks involved in the project with particularly with the use of a SLI900 ‘bridge girder erection machine'and the crane/s for erection of the precast concrete units for each of the piers.

4. On large projects such as the PIB railway, an accurate assessment of progress on the project is essential. It should be noted thata significant amount of information is generated on construction sites that maybe useful in assessing a contractor's project performance (i.e. whether the contractor is ahead of schedule or behind).The PIB project manager is investigating the tracking of project commodities for progress controlwhilst the railway is being constructed by tracking earthworks volumes, crushed rockand ballast stockpiles, quantities of rail and sleepers and viaduct construction as a minimum. By reference to the paper (see below) by Birenza RM and Hildreth JC outline how this could be undertaken.

5. Tracking project commodities could conceivably be made easier using aerial drones or UAV's to assess construction progress over the route of the railway. Outline how the above equipment could be used for aiding the tracking of the above, together with the amount of rail track that has been laid at various points in the contract.

6. Define what is meant by ‘long lead items'. Many supply itemsfor this project will be manufactured in Australia by original equipment manufacturers' (OEM's). What procedures would you put in place to ensure that the OEM's meet specified requirements and supply items are delivered to site on time?

Reference no: EM131489431

Questions Cloud

Quantity theory of money : Write the formula for the quantity theory of money and tell what it implies will happen if the money supply doubles.
What would happen to the demand for medical services : Making Predictions Suppose that your state wanted to make health care more affordable for everyone. To do this, state legislators put a series of price control.
Describe different aspects of the box and whisker plot : DENT70001 Biostatistics Assignment. Include the boxplots in your answer. Describe different aspects of the box and whisker plot
What kind of nonprice rationing system would you devise : Synthesizing You were invited to speak to a middle school class about the activities available at your school. You brought 20 ballpoint pens with the high.
Prepare a construction method statement : Prepare a Construction Method Statement (see format in reference below)outlining the steps involved in the construction of all aspects of your viaduct option.
Ceo of a small textile firm : This is the question: You are the assistant to the CEO of a small textile firm that manufactures high-quality
Define the consequences of given policy : Predicting Assume that the price of school lunches has become too high, and you need to set a price ceiling to remedy the problem. What would the consequences.
Write a two-page essay about your interview experience : Write two-page essay about your interview experience. Your essay should include introduction of your interviewee, summary of interview answer in essay format.
What is percentage price change of these bonds : Bond J has a coupon rate of 5.8 percent. Bond S has a coupon rate of 15.8 percent. what is the percentage price change of these bonds?

Reviews

len1489431

5/9/2017 3:23:03 AM

Assessment in this subject is by the satisfactory completion of three (3) Assignments. The Questions contained in this Assignment should be read in conjunction with the relevant sections of the Module notes and Bulletins that will be posted from time to time on the Blackboard for this subject All submissions should be spell checked, and all references should be correctly notated in accordance with SUT requirements.

Write a Review

Other Engineering Questions & Answers

  What are the required numbers of circuits in each group

If we require that the end-to-end GoS probability of loss for each call (internal and external) is no greater than 0.01 (1 in 100), what are the GoS probabilities of loss allowed for each of the two groups of circuits?

  Provide a graphical representation of the supply chain

Formulate the optimisation problem which will account all costs and revenues in the supply chain and optimise its operation, dominantly the logistic, such that bio-refineries get the maximum profit.

  Determine the 60-hz resistance of line

A 60-Hz, 765-kV three-phase overhead transmission line has four ACSR 900 kcmil 54/3 conductors per phase. Determine the 60-Hz resistance of line in ohms per kilometer per phase at 50°C.

  Business-website-lives and technology integrate together

Need help with writing enginnering report. Around 1500 characters. Citation and reference in APA format. The report needs the following: 1. How technologies (website and apps) relates to our daily lives;

  Working for the bahrain design company

As a Design Engineer working for the Bahrain Design Company. You are assigned to follow the design stages, in order to develop a marketing idea into a product design proposal.

  Barrel up from the ocean floor

If the barrel floats, what fraction of its volume will be above the water surface? If it sinks, what minimum tension would have to be exerted by a rope to haul the barrel up from the ocean floor?

  Explaining the fundamental processes of signal chain

Assignment - Audio connectivity and interface techniques. Learners are required to produce a report explaining the fundamental processes and operation of the following digital audio signal chain with master word-clock: 20 bit analogue to digital co..

  Find the minimum pos expression and realize the function

Construct a Karnaugh map for the logic function D = ABC + A-BC + ABC- + BC. Find the minimum SOP expression and realize the function, using AND, OR, and NOT gates.

  Electronics and communications engineering project

Write specification for electronics and communications engineering project - Establishing the scope and parameters of the projects.

  Were the works depicting uniquely american scenes

How the Abstract Expressionist artist expressed themselves using this abstract style; what were they "saying?" or what was the message of their artwork? What influenced their work?

  Differences between a shunt regulator and series regulator

Discuss what is meant by line and load regulation. Should they be high or low if you want a quality power supply?Discuss the differences between a shunt regulator and series regulator and how each works.

  Design specifications for the finite state machine.

Design Specifications for the Finite State Machine. You will code a Verilog module to implement the FSM described in this document. This lab will also require that you use the Seven-Segment Display on the DE0-CV FPGA board.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd