Prepare a complete construction budget estimate

Assignment Help Civil Engineering
Reference no: EM133145564

Question: For this assignment, your task is to prepare a complete construction budget estimate for a small office building project using the budget spreadsheet template attached to this assignment. You may suggest an alternative building of your choice if you choose to do so. This can be a project you are involved with or very familiar with, but please keep the scope manageable and preferably comparable to the one suggested.

Submit the completed Excel worksheet to the assignment on Brightspace course website. This cost will be used as the benchmark for your analysis in following assignments.

Building size

100 ft x 100 ft with 25 ft by 25 ft structural bays; 15 ft floor-floor height, two levels

Building floors

6" slab on grade with troweled finish; 24" x 24" x 12" spread footings for columns; above-grade occupied floors are poured in place concrete on 18 gauge 3" deep corrugated steel deck; roof deck is lightweight concrete on the same steel deck

Building envelope

Brick walls; loose-laid and ballasted 60 mil EPDM roof membrane

Elevators and stairs

Two 2500 lb. capacity hydraulic elevators, two sets of 3'-6" wide straight stairs with 18 risers each and wall mounted handrails both sides
Fill out each tabs in excel sheet to create a complete detailed estimate.

Reference no: EM133145564

Questions Cloud

Advantages and disadvantages of electronic banking : For the products and services listed below, note how you would use the Internet to promote the product and how you would deliver the service through your bank's
What is the risk in the context of financial decision-making : What is the risk in the context of financial decision-making? Cite some current economic situation that influences interest rates and explain its effects
New high-interest savings account : For the products and services listed below, note how you would use the Internet to promote the product and how you would deliver the service through your bank's
Explain how you determine the recoverable amount : A company acquired two (2) machines on 1 January 2015 at an amount of RM960,000 each. Explain how you determine the recoverable amount in (j) above
Prepare a complete construction budget estimate : Prepare a complete construction budget estimate for a small office building project using the budget spreadsheet template attached to this assignment
Prepare adjusted trial balance in the work sheet provided : Salary expenses for new staff-joined on December 1, 2021, not recorded amounting to $500. Prepare adjusted trial balance in the work sheet provided
Describe two organisational policies and procedures : Describe two organisational policies and procedures relating to the operation of computerised accounting systems that could be put in place to enhance security
Can assembly line technology directly affect job design : Can assembly line technology directly affect job design? How?
Calculate the depreciation for a five year asset costing : Calculate the 2021 depreciation for a 5 year asset costing $390,000 put in service on 9/21/2021

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate speed of the shockwave foamed by the bottleneck

When stationary, vehicles are spaced at average distance headway of 6 m. It may be assumed that there is a linear relationship between speed and density. When the traffic flow approaching the roadworks is 3500 vehicles per hour

  What is the max price per ton the company should pay

The supplier says it would prefer to sell the company a 65% NaOH solution and the company says the water content is immaterial as long as the equivalent costs are the same including freight.

  What deflection will occur on a mercury-water manometer

The venturi meter is in a 60 cm pipe. What deflection will occur on a mercury-water manometer connected between the upstream and throat section if the discharge is .57 m^3/s. Assume T = 20 C

  Determine what is the viscosity of the oil

The distance between the piston and the cylinder is .0011 inch. If the piston decelerates at 1.85 ft/s^2, when the speed is 19.5 ft/s. What is the viscosity of the oil. cylinder is 6 in high and 5 in long.

  Determine the reactions at the support of the cantilever

Determine the reactions at the support of the cantilever shown in Figure S1.9 . The applied loading consists of the distributed triangular force shown.

  Comment on the extent and validity of /-dominance

Comment on the extent and validity of /-dominance for the two materials under consideration.

  Compute the initial and final moisture content of the clay

A 10,000 ft3 mass of saturated clay had a void ratio of 0.962 and a specific gravity of solids of 2.71. A fill was then placed over this clay, causing it to compress. However, the volume of the solids remained unchanged. After this was complete, the ..

  Determine the magnitude and direction of the resultant

Part of the roof of a sports stadium is to be supported by the cables AB and AC. The forces the cables exert on the pylon A to which they are attached are represented by the vectors FAB and FAC.

  How many square feet of compacted cy are placed per hour

Earth whose in situ weight is 110 lb per cf and compacted weight is 124 lb per cf is placed ina a fill at rate of 280 cy per hr, measured as compacted earth. The thickness of the compacted layers is 8 in

  Plot the do vs. time in the seed bottle

You add 10 mL of sample and 5 mL of seed to bottle #1 (the sample bottle) and 20 ml of seed to bottle #2 (the seed bottle). The initial and 5-day DO in bottle #1 is 8.2 mg/I and 2.5 mg/l, respectively. The initial and 5-day DO in bottle #2 is 8.2 ..

  Estimate the total volume in thousand board feet of board

For a location in Oshkosh, WI, estimate the total volume, in thousand board feet (MBF), for 100 pieces of 2" x 8", 16-feet-long board by using CostWorks.

  How is the soil being loosened and carried away

How is the soil being loosened and carried away? What is being done with the excavated soil? What type of foundation is being installed? What provisions are being made for keeping the substructure permanently dry?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd