Prepare a communication management plan

Assignment Help Other Engineering
Reference no: EM131990905

CONSTRUCTION SITE OPERATIONS FINAL EXAM

This Examination is part of the assessment for the non OH&S component of the Construction Site Operations.

BACKGROUND -

Your company (a contracting firm) has been contracted by City of Sunshine to construct a Track and field Pavilion & associated Works as part of an upgrade to the services provided in the area. (Sunshine). City of Sunshine is the Client and the funding is provided by grants from the State Government. The new Track and field Pavilion will assist the community to engage in leisure activities in the area - where possible, all SubContractors, day labourers, relevant materials and Plant and Equipment hire are to be sourced from the local district.

During the 'Pre-Tendering' phase, all tenderers had adequate time and sufficient guidance to thoroughly inspect the site, fully review all the geotechnical information and the detailed plans for the Project and access to all relevant technical and non-technical data they needed to be fully prepared to make an informed bid. They were also given an assessment of the availability and skills of labour in the area as well as the type of material (although untested) and equipment located there. All tenderers were required to acknowledge, in writing, that they had appropriate access and professional guidance to all the necessary information they required to be able to make an informed bid.

FURTHER INFORMATION -

A. Construction time for the project was specified as 12 months. AS 4000 has been selected as the General Conditions of Contract for the project.

B. Your company has engaged a site management team (Project Manager, Contracts Administrator, Site Engineer, Site Foreman, Accounts Clerk). Client has assigned a Project Manager (Client) to act as Superintendent and a design engineer to resolve any design issues during construction. Client also has other stakeholders (local tennis club; Community leader; Council Member).

C. Early in the construction several errors are found in the plans provided by the Client. Significant redesign is required before work can continue. These errors were notified by the Contractor and Superintendent issued direction to clarify the ambiguities and corrected the errors. Contractor has submitted claims during first month for additional cost (estimated additional cost $15,000) but maintained the time for completion at 12 months.

D. During excavation and preparation of both the 'green field' and 'brown field' areas, 'objects of antiquity' were uncovered in the area where tennis pavilion to be constructed. During second month, object of antiquity was found and it was removed and handed over to the client. This set back the project by 10 days. Contractor has spent $80,000 in dealing with the removal of "object of antiquity"

E. During third month, Client decided to change the material for seating to be used in the pavilion. Your company has already ordered the material as per original drawing. Superintendent chose to direct the changes under AS 4000. Estimated additional cost in respect of this change is $100,000.

F. Your company has made progress and completed 50% of the original works (earned value) in 6 Months' time.

G. The weather is ideal for construction - the expectation, based on previous weather records of the area, had been that up to 10% of the time could be lost because of adverse weather. This has been built into the contract price by your company. As at end of 6 months there has been no claim for EOT in respect of inclement weather.

H. Expenditure Profile (AUD in thousands)

Month

1

2

3

4

5

6

7

8

9

10

11

12

Planned

50

100

120

120

120

130

130

130

120

120

100

50

Actual

65

160

235

120

130

130

 

 

 

 

 

 

Note:

1. Actual cost during first month includes claim for resolving errors.

2. Actual cost during second month includes claim for dealing with object of antiquity.

3. Actual cost during third month includes claim for change in design for seating material.

EXAM QUESTIONS -

Question 1: Project Risk and Communication

a. Your company has been requested by Client to prepare and submit a communication management plan. Prepare a communication management plan involving site management team and client's team and stakeholders.

b. Client Project Manager prepared a project risk matrix for the project to prepare the initial project budget. Prepare a project risk for this project.

Question 2: Application of AS 4000

a. AS4000 details specific lines of communication for the effective processing of all progress payments (Monthly). Detail this process as outlined by AS4000, specifically identifying all relevant clauses that authorise the process. Explain security of payment act and its application in your claim.

b. Explain how your company submitted the claims for dealing with ambiguities and errors in the documents with relevant clauses from AS 4000.

c. Your company decided to make 'Claims for Variation' for the additional works arising from the re-design of the seating. Your claim should include possible surplus material or other alternative ways to deal with your order. What is the relevant clause under which Superintendent must have issued the direction to change the seating material? Explain with reasons.

d. Explain how your company dealt with discovery of 'object of antiquity' and how the Superintendent dealt with the claims for additional cost and time.

e. Your company noticed that the bolts shown on the drawings to fix the seating's were specified as galvanized iron bolts. Your company advised the Client that stainless steel bolts would be appropriate to avoid corrosion. Superintendent is considering your company's suggestion. Explain how the Superintendent and your company go about implementing the change of material for bolt.

Question 3: Earned Value Analysis

a. Based on the information provided in section H and other sections under "Further Information" carry out earned value analysis at the end of 6th month and calculate PV; EV; AC; CV; SV; CPI, SPI; BAC.

b. Estimate the cost at completion (EAC) using different methods;

I. If the CPI is expected to be the same for the remainder of the project,

II. If future work will be accomplished at the planned rate; and

III. If both the CPI and SPI influence the remaining work;

Question 4: Report

a. Prepare a draft monthly report to the client detailing the status of the project as at the end of 6th month.

Question 5 : Estimating VOWD (Value of Work Done) and Accruals

In a water pipeline project, following information has been provided to the Contract administrator.

Contract Scope: Procure, deliver, install and test 3 Km long 300mm dia pipeline from point A to point B as shown in the drawings and specification.

Contract period: 8 Months

Bill of Quantities

Description

Qty

Unit

Rate

Currency

Amount (USD)

Amount (AUD)

Procurement and delivery of 300mm dia pipes at site

3000

M

200

USD

600,000

 

Excavate trench and lay the pipe as specified.

3000

M

120

AUD

 

360,000

Testing of pipeline as specified

3000

M

30

AUD

 

90,000

Rates are inclusive of overheads and profit.

At the end of 4th month into the project,

  • 30% of pipes have been delivered to the site and accepted by the Superintendent as complying with the specification.
  • Contractor has laid 20% of the pipes and tested 50% of the laid pipes.
  • Invoices for 20% of delivery of pipes (3KM total); 10% of pipe in place; 0% for testing have been paid at the end of 3rd month.

Exchange rate for the end of 3rd month; 1AUD = 0.75 USD as paid in invoices.

Exchange rate for the end of 4th month (as provided by finance department); 1AUD = 0.80 USD

a. Estimate the VOWD (in AUD) as at end of 4th month and accrual (accounting) (in AUD).

Attachment:- Assignment File.rar

Verified Expert

The solution is about the accounting and it was assigned for the plagiarism free work. The solution is plagiarism free except the tables and the figures whereas the rest of the content is changed as per the requirement.

Reference no: EM131990905

Questions Cloud

Discuss the pentagon unprepared for attack : Discussion the Pentagon Unprepared for Attack. Explain why the allegations that the Pentagon is not prepared for an attack were made.
Explain market stabilization : Explain market stabilization. What were some of the reasons for the decline in Facebook's stock price after its IPO?
Create and post a project plan : Create and post a project plan that describes how you will complete a full draft of your literature review in the time available.
What is required rate of return : Kollo Enterprises has a beta of 0.70, the real risk-free rate is 2.00%, What is Kollo's required rate of return?
Prepare a communication management plan : CSM80007- CONSTRUCTION SITE OPERATIONS FINAL EXAM - Prepare a communication management plan involving site management team
Identify different tools and techniques : PPMP 20014 - Complex Project Management - Explain the causes, environments, and properties of complex projects - Identify different tools and techniques
Discuss open research questions and possible future research : discuss two to four open research questions and possible future research directions regarding organizational change, ideally within your concentration.
Explain differences between the two pools WAM and WAL : What are the stated maturity, WAC, WAM, and WAL of each pool and the combined pool? Explain differences between the two pools’ WAM and WAL.
What were long-term debt and total liabilities : What were Wallace’s long-term debt and total liabilities in 2015? How much new long-term debt financing will be needed in 2016?

Reviews

len1990905

5/21/2018 6:33:00 AM

Deadline: Needed by Wednesday Afternoon. Course : Masters in construction and infrastructure management. Subject: Construction site operations. I need the assignment by Wednesday evening with proper answers. I need a very good experienced one to do this. Please don't give to someone who doesn't know the subject. please, I need to pass in this subject. So only.

len1990905

5/21/2018 6:32:51 AM

This Examination is part of the assessment for the non OH&S component (65%) of the Construction Site Operations subject in Semester One (1), The full details of the assessment of this component were provided, in writing, at the commencement of the Semester. As a reminder, this examination is worth 45% of the total marks. Instructions for this Examination are outlined in Section 4. Where ‘Contract Administrator’ is used in this Examination paper, it has the same meaning as ‘Superintendent’ used in AS4000 – GENERAL CONDITIONS OF CONTRACT.

len1990905

5/21/2018 6:32:44 AM

EXAMINATION INSTRUCTIONS - Please read the paper and the questions carefully. Each of the five (5) questions must be answered - specific marks are allocated to each question and, if relevant, to the elements of each question. Therefore, it is imperative that you read all the ‘Background’ and ‘Further Information’ carefully, at least a couple of times, before you commence your responses to any of the questions. Background and Further information are relevant for first four questions and question 5 is to be attempted without reference to the background and further information.

len1990905

5/21/2018 6:32:38 AM

You may wish to create additional background material and/or assumptions about your company’s Project to assist in developing your responses. However, if you do so, you must clearly outline what additional background information you have created at the very beginning on Page 1 of your response prior to answering any of the questions. The response should be no more than 1500 words including any Appendices. References are to be used with the author and source clearly stated and included as either a ‘bibliography’ at the end of your paper or in ‘footnotes’ at the bottom of the relevant page.

len1990905

5/21/2018 6:32:30 AM

A hard copy is to be delivered no later than 5.00pm, Friday 25th at the address in (f) below. The hard copy response is to be delivered, by the due date, to: - Box 44 Sungkon Moon Mail Box, 7 th Floor, Advanced Technologies Centre (ATC Building), Burwood Rd., Hawthorn, 3122 NOTE: Only a hard copy will be accepted as formal submission. You can send an email version for information purpose. It will be considered only for information purpose. Acknowledgement of receipt of your paper will not be provided.

Write a Review

Other Engineering Questions & Answers

  Characterization technology for nanomaterials

Calculate the reciprocal lattice of the body-centred cubic and Show that the reciprocal of the face-centred cubic (fcc) structure is itself a bcc structure.

  Calculate the gasoline savings

How much gasoline do vehicles with the following fuel efficiencies consume in one year? Calculate the gasoline savings, in gallons per year, created by the following two options. Show all your work, and draw boxes around your answers.

  Design and modelling of adsorption chromatography

Design and modelling of adsorption chromatography based on isotherm data

  Application of mechatronics engineering

Write an essay on Application of Mechatronics Engineering

  Growth chracteristics of the organism

To examine the relationship between fermenter design and operating conditions, oxygen transfer capability and microbial growth.

  Block diagram, system performance and responses

Questions based on Block Diagram, System Performance and Responses.

  Explain the difference in a technical performance measure

good understanding of Mil-Std-499 and Mil-Std-499A

  Electrode impedances

How did this procedure affect the signal observed from the electrode and the electrode impedances?

  Write a report on environmental companies

Write a report on environmental companies

  Scanning electron microscopy

Prepare a schematic diagram below of the major parts of the SEM

  Design a pumping and piping system

creating the pumping and piping system to supply cool water to the condenser

  A repulsive potential energy should be a positive one

Using the data provided on the webvista site in the file marked vdw.txt, try to develop a mathematical equation for the vdW potential we discussed in class, U(x), that best fits the data

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd