Printware Products, Inc. produces printers for wholesale distributors. It has just completed packaging an order from Hawes Company for 450 printers. Before the order is shipped, the controller wants to compare the unit costs computed under the company's new activity-based costing system with the unit costs computed under its traditional costing system. Printware's traditional costing system assigned overhead costs at a rate of 240 percent of direct labor cost.
Data for the Hawes order are as follows: direct materials, $17,552; purchased parts, $14,856; direct labor hours, 140; and average direct labor pay rate per hour, $17.
Data for activity-based costing related to processing direct materials and purchased parts for the Hawes order follow.
Activity Cost Driver Activity Cost Rate Activity Usage
Engineering systems design Engineering hours $ 28 per engineering hour 18 engineering hours
Setup Number of setups $ 36 per setup 12 setups
Parts production Machine hours $ 37 per machine hour 82 machine hours
Product assembly Assembly hours $ 42 per assembly hour 96 assembly hours
Packaging Number of packages $ 5.60 per package 150 packages
Building occupancy Machine hours $ 10 per machine hour 82 machine hours
Required
If required, round the per unit answers to the nearest cent.
1. Use the traditional costing approach to compute the total cost and the product unit cost of the Hawes order.
Total cost $
Product unit cost $
2. Using the cost hierarchy, identify each activity as unit level, batch level, product level, or facility level.
Engineering systems design
Setup
Parts production
Product assembly
Packaging
Building occupancy
3. Prepare a bill of activities for the activity costs.
Printware Products, Inc.
Bill of Activities
Hawes Order
Activity Activity Cost Rate Cost Driver Level Activity Cost
Unit level
Parts production $ per machine hour machine hours $
Product assembly $ per assembly hour assembly hours
Packaging $ per package packages
Batch level
Setup $ per setup setups
Product level
Engineering systems design $ per engineering hour engineering hours
Facility level
Building occupancy $ per machine hour machine hours
Total activity costs assigned to job $
Total units of job
Activity costs per unit $
4. Use ABC to compute the total cost and product unit cost of the Hawes order.
Cost summary
Direct materials $
Purchased parts
Activity costs
Total cost of order $
Product unit cost $
5. What is the difference between the product unit cost you computed using the traditional approach and the one you computed using ABC?
Between education and economic development
: Explain the link between education and economic development found by Easterlin. Does higher education for the elite or basic education for the masses have a larger impact on development?
|
Evaluate the efficiency and reliability
: From the e-Activity, examine at least three (3) benefits and three (3) drawbacks that an organization or individual could experience using virtualization. Recommend one (1) individual or organization that would highly benefit from using virtualiza..
|
Evaluate the compression index and the recompression index
: Use the consolidation data from Problem 8-20 to compute the settlement of a structure that adds 150 kPa to the already existing overhurden pressure of 120 kPa at the middle of a 6 m thick layer.
|
Effectiveness of the market structure for the company
: Using the regression results and the other computations from Assignment 1, determine the market structure in which the low-calorie frozen, microwavable food company operates.
|
Prepare a bill of activities for the activity costs
: Prepare a bill of activities for the activity costs. What is the difference between the product unit cost you computed using the traditional approach and the one you computed using ABC?
|
Determine the compressive stress in the column
: A hollow circular mild steel column of external diameter 300 mm and internal diameter of 250 mm carries an axial load of 1500 kN. Determine the compressive stress in the column
|
What upgrade options exist for moving from server
: What upgrade options exist for moving from Server 2008 (R2) to Server 2012? What limitations or caveats should be considered when upgrading? Would you typically recommend a clean install or an in-place upgrade when attempting to move a service fr..
|
What are the total costs for an output
: a. Assuming the total costs per day C is linearly related to the total output per day (X), write an equation relating these two quantities. b. What are the total costs for an output of 12 boards per day?
|
Calculate direct materials cost and efficiency variances
: Calculate direct materials cost and efficiency variances. Calculate direct labor cost and efficiency variances. Prepare journal entries to record the use of both materials and labor for March for the company.
|