Preliminary scope statement for the project

Assignment Help Project Management
Reference no: EM133244351

CASE STUDY

Trans LAN Project

Trans Systems is a small, information systems consulting firm located in Meridian, Louisiana. Trans has just been hired to design and install a local area network (LAN) for the city of Meridian's social welfare agency. You are the manager for the project, which includes one Trans professional and two interns from a local university. You have just finished a preliminary scope statement for the project (see below). You are now brainstorming potential risks associated with the project.

Project Scope Statement:
Objective: To design and install a new local area network (LAN) within one month with a budget not to exceed $90,000 for the Meridian Social Service Agency and with minimum disruption to ongoing operations.

Deliverables:

  • 20 Workstations and 20 laptop computers
  • Server with dual-core processors on Windows R2 server and workstation operating system (Windows 7)
  • Migration of existing databases and programs to new system
  • Four hours of introductory training for client's personnel
  • 16 hours of training for client network administrator
  • Fully operational LAN system

Milestones:

  • Hardware by Jan 22
  • Setting users' priority and authorization by Jan 26
  • In-house whole network test completed Feb 1
  • Client site test completed Feb 2 and Training completed by Feb 16

Technical Requirements:

  • Workstations with 17-inch flat panel monitors, dual-core processors, 4GB RAM, DVD +RW, wireless card, Ethernet card, 500 GB Hard disk laptops with 12-inch display and similar specs to workstations
  • Wireless network interface cards and Ethernet Connections
  • System must support Windows Vista/Windows 7 platforms
  • System must provide secure external access for field workers' constraints
  • On-site work to be done after 8 pm and before 7 am (Mon - Sat)
  • System maintenance and repair only up to one month after final inspection
  • Warranties transferred to client
  • Only responsible for installing software designated by the client. Client will be billed for additional training beyond that prescribed in the contract.
    Customer Review: Director of the city of Meridian's Social Service Agency
  • Read the case study carefully and answer the following questions:

1. Identify potential risks associated with this project. Try to come up with at least five different risks.

2. Develop a Risk Assessment Matrix that accurately calculates the likelihood, impact, and opportunity associated with the risks that you have identified.

3. Make an action plan that appropriately responds to these risks.

Reference no: EM133244351

Questions Cloud

Identify one business requirements : Identify one business requirements that would need to be addressed as part of the business problem (Inventory management) for ClubIT. The business requirements
How does hvac systems visually integrate with another system : How does HVAC systems visually integrate with another system (e.g. site system, interior systems etc)
Accomplish to show evidence of achieving the goal : Identify and describe at least one resource that will will use to learn about how to improve the skill.
Would likely be upheld by supreme court as constitutional : Which action would most likely be upheld by the Supreme Court as constitutional?
Preliminary scope statement for the project : Trans Systems is a small, information systems consulting firm located in Meridian, Louisiana. Trans has just been hired to design and install a local area netwo
What are the measures that are used to assess p4p : What are the measures that are used to assess P4P and the sources of data that are used to create P4P performance measures.
Identify possible risks in the case study project : Kloppenborg et al. (2018:366) defines identify risk as the process of determining which risks might affect the project and documenting their characteristics. Th
Types of entrants does a landowner face the greatest duty : Under the traditional categories of duty to entrants upon land or real estate, toward which types of entrants does a landowner face the greatest duty?
Discuss several branding decisions : Q1. Explain the organization's product plan for a personal fitness company

Reviews

Write a Review

Project Management Questions & Answers

  Confidence in the ability of humankind

Do you have confidence in the ability of humankind to overcome environmental challenges or do you believe that the planet is doomed? Please explain your position clearly.

  Benefit of using a Stakeholder Engagement Assessment Matrix

Power-Interest Matrix as a model used to analyse and align program stakeholders' goals with the program goals - Identify five examples of factors upon

  Sales promotions advertising decision sequence model

Explain why you agree or disagree with the contention that the APIC-type model is useful as a framework for direct marketers or sales promoters to operate within.

  What are key advantages of using project management software

What are the key advantages of using project management software? What is a work breakdown structure, and how is it useful for project planning?

  Who must bear the loss in given condition

On the night of July 2, the tractor was destroyed by fire of unknown origin. Neither Stein nor Beal had any fire insurance. Who must bear the loss?

  Information about hardware and system software

What is an RFP, and how do analysts use one to gather information about hardware and system software?

  Responding to risk - four alternativesexplain what are the

responding to risk - four alternativesexplain what are the four alternatives a project organization can adopt in

  Define the project scope

After you have the project scope management plan developed, define the project scope

  Non-profit organization with financial data

A business organization for which a close friend or relative works and to which you have access - Any non-business oriented organization such as a non-profit organization with financial data available to you

  Shared activity leadership values

This unit is about the values and principles that underlie leadership behaviour. For this Shared Activity, you will discuss whether leadership values are universal or whether they can be contextual or culturally derived.

  What is the overall reliability of the system

PMAN 639: PROJECT QUALITY MANAGEMENT FINAL EXAM. A product is made up of two subsystems in series. What is the overall reliability of the system

  Performance evaluation and video presentation assignment

Performance Evaluation and Video Presentation Assignment help and solution, evaluate the performance of each of the three projects.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd