Predicting Project Duration

You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?

ID| Description | Predecessor | Time/Days
A | Pour Foundation | None | 3
B | Erect frame | A | 4
C | Roof | B | 4
D | Windows | B | 1
E | Doors | B | 1
F | Electrical | B | 3
G | Rough-in frame | C,D,E,F | 2
H | Door Opener | E, F | 1
I | Paint | G,H | 2
J | Clean up | I | 1

Reference no: EM13363046

Questions Cloud

Characteristics of high-performing project management : characteristics of high-performing project management teamswhat are the four most important characteristics of
Project management closeout checklistprepare a closeout : project management closeout checklistprepare a closeout checklist for a project including details on what steps you
Change management in a projectdescribe the concept of the : change management in a projectdescribe the concept of the change management process within a project and give two
Find the project sponsor we are allowed to use anyone even : find the project sponsor we are allowed to use anyone even make up a name amp customer. write 600-750 words about your
Predicting project durationyou have signed a contract to : predicting project durationyou have signed a contract to build a garage for the simpsons. you will receive a 500 bonus
Project management models and information systemsenvision a : project management models and information systemsenvision a new information system for some business function for
Project management models and information systemsenvision a : project management models and information systemsenvision a new information system for some business function for
Project management critical pathsplease help me to solve : project management critical pathsplease help me to solve the following problemyou are working on a project that has 12
Project management analysis of critical pathssuppose the : project management analysis of critical pathssuppose the length of critical path in a project is 50 days. the

Reviews

Write a Review

Project Management Questions & Answers

  Cost and time are critical components of projects

While cost and time are critical components of projects, how would you define the quality of a project?

  Inclusion of a sound culture and adoption

Do you think the inclusion of a sound culture and adoption of tried and tested methodologies and standards can improve this process and Or is this too idealistic or simplistic

  What ways does this hinder a project

Some companies choose not to tie resources to their projects. In what ways does this benefit a project and In what ways does this hinder a project?

  Investment criteria for selection of investment project

Describe which three of these investment criteria you recommend for use at your current (or a former) company for the selection of investment projects.

  Describe the levels of uncertainty

Describe the levels of uncertainty and complexity for the project and determine what the project manager should communicate to the customers about the project unknowns.

  Criteria for selecting items for analysis of project

How do you determine if the project is "sensitive" to the specific items? What are the criteria for selecting items for analysis?

  A project can be closed for several reasons.

A project can be closed for several reasons.

  Integrate the wbs with the organization

Show the importance to fully integrate the WBS with the organization

  Members of the project team

Explain what are the roles, responsibilities, and authority assigned to project managers and various other members of the project team.

  Direct impact on ethical climate of organization

Leaders must understand their actions have a direct impact on the ethical climate of the organization please describe

  Show the benefits of matrix structure and project reports

Explain which type of organizational form fosters teamwork in the best manner and what are the major reasons for having project managers report higher and higher in the organizational structure?

  Evaluate the operating cash flows of the project

Evaluate the operating cash flows of the project for the next 6 years id the firm's tax bracket is 35 percent - Has a new mower line that can generate revenues

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd