Predecessor activities

Assignment Help Project Management
Reference no: EM13893029

1.Define predecessor, successor, and parallel activities. Give a real world example of each

Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.

Successor activities - activities that must follow a particular activity in some type of sequence. Ex: a program must be tested and then documented after it is compiled.

Parallel activities - an activity or task that can be worked at the same time as another activity. Ex: Design web page layouts and set-up server
 

2. In the context of critical chain project management, what is resource contention?  

3.Define the following and give a real world example of each (other than the ones described in the text book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.  

4.     Assume the following activities for a project along with their estimated durations and predecessors. Describe how critical path analysis would be applied to this project, and calculate the critical path. Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?  

Hint: Start with the following steps:

a.       Draw AON diagram

b.       Calculate Possible Activity paths

c.       Identify critical path

 

Activity

Estimated Duration in Days

Predecessor

A

2

None

B

4

A

C

3

A

D

1

C,B

E

1

C,D

F

3

D,E

G

2

F

Critical Path: A-B-G-F-H

Slack/Float: amount of time an activity can be delayed before it delays the project Expedite/Crash: adding resources to an activity on the critical path to shorten duration Fast Tracking: completing activities in parallel to shorten critical path 

5.     What are the seven IT project risk management processes?  

6.     What is a risk response plan? What should be included? 

7.     Compare the three types of project risk: known, known-unknown, and unknown-unknown. Give an example (not discussed in the text book) of each

8.      Describe the qualities of a good project metric.  

9.       Given the following information, is the Project in trouble?

Calculate: 

a.       Cost Variance (CV) : (CV) = EV AC

b.      Schedule Variance (SV):  (SV) = EV PV

c.       Cost Performance Index  (CPI) : (CPI) = EV/AC

d.      Schedule Performance Index (SPI):  (SPI) = EV/PV 

10.  What are the key differences (4-5) between the Agile Project Management approach and Waterfall (Traditional Project Management) 

11.  What was your favorite topic in this course? 

Reference no: EM13893029

Questions Cloud

What are baseline dates based on : What are baseline dates based on? 2. What is variance, and how is it calculated? 3. What do positive and negative variance indicate? 4. What table do you apply to the task sheet to see baseline dates? What table do you apply to see actual dates? What..
Create a profile of the target consumer of tide : Explain how psychographic information is employed to create a profile of the target consumer of Tide. I need two hundred words with references.
Learning of employees and customers : In what ways has the learning of employees and customers changed as a result of their ability to use the Web, and how would this change the interaction between them during the purchasing process?
Implement a matrix class for two-by-two matrices : Implement a Matrix class for 2-by-2 matrices. Include a default constructor, a copy constructor, an inverse() function that returns the inverse of the matrix.
Predecessor activities : Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.Successor activities - activities that must follow a particular activit..
What is the p-value for the test : The life in hours of a battery is known to be approximately normally distributed, with standard deviation s = 1.25 hours. A random sample of 10 batteries has a mean life of x ¯=40.5 hours. Is there evidence to support the claim that battery life ex..
Historians rely on primary sources to construct a picture : Historians rely on primary sources to construct a picture of the past
Implement a point class for two-dimensional points : Implement a Point class for two-dimensional points (x, y). Include a default constructor, a copy constructor, a negate() function to transform the point into its negative, a norm() function to return the point's distance from the origin (0,0), an..
In analyzing the circumstances surrounding the war of 1812 : In analyzing the circumstances surrounding the War of 1812

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd